Work Planned upto 3/7/2010 |
Completed / Progress |
Remarks |
|
P3-P4 Span
|
|
Road Blocked for P3-P4 span work. |
|
2nd stage stressing |
Completed |
|
|
Concreting of Slab |
Completed |
|
|
Approval of GAD by railways (Railway Portion) |
Approved |
Approved on 1-5-10 |
|
Preparation of Design and Drawing |
In progress |
|
|
Under Pass Wall concreting 3rd lift and slab |
In progress |
|