Prevoius Weekly Reports

   17-06-2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR  SIDE

100%

17

83%

0

15.00%

12.00%

3.00%

15.00%

46 days

 

10

RE/R WALL M.C SIDE

100%

9

91%

0

2.00%

0.00%

2.00%

0.00%

46 days

Concreting of the raft portion in RCC retaining wall in progress.Total length of the concreting completed is 32 metres.

11

BEAM/SLAB SHORNUR  SIDE

3

0

3

0

0

0

0

0*

31 days

Staging works at AP1-P1 progressing slowly.Pedestal reinforcement and shuttering completed for AP1,P1 location.

12

BEAM/SLAB M.C SIDE

12

5

7

0

1

1

4

1

83 days

Concreting of the beam and deck slab of the span P10-P11 completed.Bottom shuttering of the span P8-P9 nearing completion.Beam reinforcement for P8-P9 started.

13

HR/FP/KERB SHORNUR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

11 days

 

14

HR/FP/KERB M.C SIDE

100%

7

93%

0

3.00%

2.00%

0.00%

1.00%

 

kerb concreting of one side of span P10-P11 completed

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

16

Deck Slab

 

 

 

 

 

 

 

 

 

 

17

Utility shifting

 

 

 

 

 

 

 

 

 

 

 

Availability of Men

 

 

 

 

 

 

 

Date

06-11-2011

06-12-2011

13-6-2011

14-6-2011

15-6-2011

16-6-2011

17-6-2011

Nof labours

51

51

32

36

38

38

38

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

 

 

Required

Available

Remarks

 

 

 

 

Fine aggregate {cft}

600

410

 

 

 

 

 

Cement(bag)

630

350

stock will be replendished soon.

 

 

 

 

Steel inT

11

16

sufficient material available at the site

 

 

 

 

Coarse Aggreagate (cft)

400

500

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

 

 

Utilities to be shifted

 

Remarks

 

 

 

 

 

BSNL

COMPLETED

 

 

 

 

 

 

KSEB

COMPLETED

 

 

 

 

 

 

KWA

COMPLETED

 

 

 

 

 

 

Others

COMPLETED

 

 

 

 

 

 

 
Back
 
    
BOTTOM SHUTTERING (17.06.2011)

    
    
RAFT CONCRETING (16.06.2011)

    
    
BOTTOM SHUTTERING OF SPAN P8-P9 (15.06.2011)

    
    
KERB CONCRETING (15.06.2011)

    
 
    
PEDASTAL REINFORCEMENT (14.06.2011)

    
    
HAND RAIL CASTING (13.06.2011)

    
    
CONCRETING OF DECK SALB P10-P11 (12.06.2011)

    
 
    
CONCRETING OF BEAM P10-P11 (11.06.2011)

      
 

 

 

 

 

 

 

 