|
ROB at Koratty
PROGRESS OF ROB WORK AS ON 10.07.2010 |
Work Planned upto 10-7-2010 |
Completed/ Progress |
Remarks |
P3-P4 Span |
|
|
2nd stage stressing |
Completed |
|
Concreting of Slab |
Completed |
|
Approval of GAD by railways (Railway Portion) |
Approved |
Approved on 1-5-10 |
Preparation of Design and Drawing |
In progress |
|
Under Pass Wall concreting 3rd lift and slab |
In progress |
|
|