Revised Progress Report For Ponnurunni ROB for the week ending on 17-06-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE (A)PLRVTM SIDE |
31 |
28 |
3 |
0 |
0 |
0 |
0 |
0 |
|
KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS |
2 |
PILE(R) PLRVTM SIDE |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
|
3 |
PILE (A)VYTLA SIDE |
40 |
0 |
40 |
0 |
0 |
0 |
0 |
0 |
|
4 |
PILE(R) VYTLA SIDE |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
|
5 |
PILE CAP(A) PLRVTM SIDE |
8 |
1 |
7 |
2 |
2 |
1 |
2 |
2 |
|
6 |
PILE(R) PLRVTM SIDE |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
7 |
PILE (A)VYTLA SIDE |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
|
8 |
PILE(R) VYTLA SIDE |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
9 |
RE WALL PANEL |
370 |
71 |
300 |
0 |
42 |
28 |
14 |
42 |
|
|
Status of utility shifting
KWA
|
Joint Inspection with Axe and AE,KWA,Pallimukku
|
21.2.2011
|
DDsubmitted to EE,KWA on 9.5.2011,
(KWA Tendered the work
|
Joint Inspection with AE,AXE and EE KWA
|
2.4.2011
|
BSNL
|
Joint Inspection with DE, BSNL,Palarivattom
|
23.3.2011
|
DE, informed that there is no BSNL cable to be removed
|
Joint Inspection with SDE,BSNL,Vytilla
|
11.4.2011
|
Estimate is to be received
|
BPCL
|
Joint Inspection with BPCL
|
24.3.2011
|
Span RP1-P9 changed
|
KSEB
|
Joint Inspection with Sub Engineer, KSEB
|
23.3.2011
|
Shifting isin progress
|
Joint Inspection with AE,KSEB,Vyttilla
|
11.4.2011
|
|