   weekly progress 17.6.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 17-06-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE (A)PLRVTM SIDE 31 28 3 0 0 0 0 0   KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS
2 PILE(R) PLRVTM SIDE 6 0 6 0 0 0 0 0  
3 PILE (A)VYTLA SIDE 40 0 40 0 0 0 0 0  
4 PILE(R) VYTLA SIDE 6 0 6 0 0 0 0 0  
5 PILE CAP(A) PLRVTM SIDE 8 1 7 2 2 1 2 2  
6 PILE(R) PLRVTM SIDE 1 0 1 0 0 0 0 0  
7 PILE (A)VYTLA SIDE 9 0 9 0 0 0 0 0  
8 PILE(R) VYTLA SIDE 1 0 1 0 0 0 0 0  
9 RE WALL PANEL 370 71 300 0 42 28 14 42    

 

 Status of utility shifting

KWA

Joint Inspection with Axe and AE,KWA,Pallimukku

21.2.2011

DDsubmitted to EE,KWA on 9.5.2011,

(KWA Tendered the work

Joint Inspection with AE,AXE and EE KWA

2.4.2011

BSNL

Joint Inspection with DE, BSNL,Palarivattom

23.3.2011

DE, informed that there is no BSNL cable to be  removed

Joint Inspection with SDE,BSNL,Vytilla

11.4.2011

Estimate is to be received

BPCL

Joint Inspection with BPCL

24.3.2011

Span RP1-P9 changed

KSEB 

Joint Inspection with Sub Engineer, KSEB

23.3.2011

Shifting isin progress

Joint Inspection with AE,KSEB,Vyttilla

11.4.2011  

 
Back
 
    
SHIFTED ELETRIC POST AT P2

    
    
SHIFTED ELETRIC POST AT A1.

    
    
RE WALL PANEL CONCRETING-

    
    
PILECAP CONCRETING P15--2

    
 
    
P15 PILECAP BACK FILLED

    
    
P13 PILECAP-SHORING

      
 

 

 

 

 

 

 

 