   10-06-2011
    

 

Revised Progress Report For MulankunnathukavuROB for the week ending on 10-06-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR  SIDE

100%

9

91%

0

10.00%

8.00%

 

15.00%

53 days

 

10

RE/R WALL M.C SIDE

100%

9

91%

0

2.00%

0.00%

2.00%

2.00%

53 days

Concreting of the raft portion in progress in the RCC Retaining wall .Concreting was done only upto  25% of the raft .Balance work is planned for the next week

11

BEAM/SLAB SHORNUR  SIDE

3

0

3

0

0

0

0

0*

38 days

Levellng and rolling of the span AP1-P1 completed for starting the staging works.Staging works commenced today.

12

BEAM/SLAB M.C SIDE

12

5

7

0

1

0

4

1

90 days

Reinforcement tying of the deck slab of the span P10-P11 in progress.Staging works of the span P8-P9 completed 90%

13

HR/FP/KERB SHORNUR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

18 days

 

14

HR/FP/KERB M.C SIDE

100%

7

93%

0

3.00%

0.00%

0.00%

3.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

16

Deck Slab

 

 

 

 

 

 

 

 

 

 

17

Utility shifting

 

 

 

 

 

 

 

 

 

 

 

Availbilityof Men

 

 

 

 

 

 

 

Date

06-04-2011

06-05-2011

06-06-2011

06-07-2011

06-08-2011

06-09-2011

06-10-2011

Nof labours

39

47

47

51

51

51

51

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

 

 

Required

Available

Remarks

 

 

 

 

Fine aggregate {cft}

500

610

 

 

 

 

 

Cement(bag)

630

770

 

 

 

 

 

Steel inT

11

20

sufficient material available at the site

 

 

 

 

Coarse Aggreagate (cft)

400

710

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

 

 

Utilities to be shifted

 

Remarks

 

 

 

 

 

BSNL

COMPLETED

 

 

 

 

 

 

KSEB

COMPLETED

 

 

 

 

 

 

KWA

COMPLETED

 

 

 

 

 

 

Others

COMPLETED

 

 

 

 

 

 

 
Back
 
    
06.06.2011

    
    
07.06.2011

    
    
08.06.2011

    
    
09.06.2011

    
 
    
10.06.2011

    
    
10.06.2011

      
 

 

 

 

 

 

 

 