Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053622
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress report as on 10/06/2011
    

 

Progress Report For Payyannur ROB for the week ending on 10-06-2011
Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance  work up to last week
Cumulative delay in Qty up to last week
Work  planned  during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work  Planned for next week
Remarks
1
PILE THRIKKARIPUR  SIDE
33
33
0
0
0
0
0
0
 
2
PILE EZHIMALA SIDE
27
27
0
0
0
0
0
0
 
3
PILE PAYYANNUR SIDE
27
27
0
0
0
0
0
0
 
4
PILE CAP THRIKKARIPUR  SIDE
11
11
0
0
0
0
0
0
 
5
PILE CAP EZHIMALA SIDE
9
9
0
0
0
0
0
0
 
6
PILE CAP PAYYANNUR SIDE
9
9
0
0
0
0
0
0
 
9
PIER THRIKKARIPUR  SIDE
11
11
0
0
0
0
0
0
 
8
PIER EZHIMALA SIDE
9
9
0
0
0
0
0
0
 
9
PIER PAYYANNUR SIDE
9
9
0
0
0
0
0
0
 
10
PIER CAP THRIKKARIPUR  SIDE
11
9
2
2
2
0
2
2
 
11
PIER CAP EZHIMALA SIDE
9
8
1
1
1
0
1
1
 
12
PIER CAP PAYYANNUR SIDE
9
7
2
2
2
2
1
1
 
16
RE/R WALL THRIKKARIPUR  SIDE
100%
45%
55%
0
0.00%
0.00%
0.00%
0.00%
 
17
RE/R WALL EZHIMALA SIDE
100%
45%
55%
0
0.00%
0.00%
0.00%
0.00%
 
18
RE/R WALL PAYYANNUR SIDE
100%
0
100%
0
0.00%
0.00%
100.00%
0.00%
 
19
BEAM/SLAB  Staging Thrikkaripur side
9
4
5
3
1
0.7
4
1
 
20
BEAM/SLAB  Bar bending and Fixing Thrikkaripur side
9
3.4
5.6
3
1
0.6
4
1
 
21
BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side
9
3
6
3
0
*0
4
1
girder concreting done
22
BEAM/SLAB  Staging Ezhimala side
8
1
7
3
0
0
4
1
 
23
BEAM/SLAB  Bar bending and Fixing Ezhimala side
8
1
7
3
0
0
4
2
 
24
BEAM/SLAB  Shuttering  and Concreting  Ezhimala side
8
1
7
3
0
0
4
1
 
25
BEAM/SLAB  Staging Payyanur side
9
4
5
3
0
0.6
4
1
 
26
BEAM/SLAB  Bar bending and Fixing Payyanur side
9
3.5
5.5
3
0
0.5
4
1
 
27
BEAM/SLAB  Shuttering  and Concreting Payyanur side
9
2
7
3
0
2
4
 
 
28
BEAM/SLAB THRIKKARIPUR  SIDE
10
2
8
3
0
0
4
0
 
29
BEAM/SLAB EZHIMALA SIDE
8
1
7
3
0
0
4
0
 
30
BEAM/SLAB PAYYANNUR SIDE
9
2
7
3
0
2
4
0
 
31
HR/FP/KERB THRIKKARIPUR  SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
32
HR/FP/KERB EZHIMALA SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
33
HR/FP/KERB PAYYANNUR SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
34
BC/PAINTING
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
 
 
 
 
 
 
 
 
 
 
 
 
Note: Progress review done based on the revised Program (rev-01)
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Availbility of Men
 
 
 
 
 
 
 
 
 
 
Date
 
06-04-2011
06-05-2011
06-06-2011
06-07-2011
06-08-2011
06-09-2011
06-10-2011
 
 
Nof labours
 
87
86
87
60
87
86
87
 
 
 
 
 
 
 
 
 
 
 
 
 
Material Stocking Status
 
 
 
 
 
 
 
 
 
 
 
Required
Available
Remarks
 
 
 
 
 
 
 
Coarse Aggreagate (m3)
 
 
 
 
 
 
 
 
 
 
Fine Aggreagate(m3)
28
8
 
 
 
 
 
 
 
 
Cement(bag)
400
250
 
 
 
 
 
 
 
 
Steel(MT)
10
300
 
 
 
 
 
 
 
 
Back
 
    
P22_23 SLAB CONCRETED (09/06/2011)

    
    
P20_P21 STAGGING (09/06/2011)

    
    
P4_P5 SLAB STAGGING (09/06/2011)

    
    
HANDRAIL CASTING (09/06/2011)

    
 
    
AP3 PIER BEAM (10.06.2011)

    
    
AP1 DIRT WALL (08.06.2011)

      
 

 

 

 

 

 

 

 

Untitled Document