Si No
Activity Description
Total Quantity
Cumulative progress uptolast week
Balance work up to last week
Cumulative delay in Qty up to this week
Work planned during the week
Actual work done during the week
Work Planned for next week
Remarks
1
RE/R WALL PALAKKAD SIDE
100%
62%
38%
0
2.00%
2
RE/R WALL MOYAN SCHOOL SIDE
18%
82%
3.00%
3
BEAM/SLAB Staging PALAKKAD SIDE
4
BEAM/SLAB Bar bending and Fixing PALAKKAD SIDE
5
BEAM/SLAB Bar Shuttering And Concreting PALAKKAD SIDE
6
BEAM/SLAB Staging MOYAN SCHOOL SIDE
7
BEAM/SLAB Bar bending And Fixing MOYAN SCHOOL SIDE
8
BEAM/SLAB Shuttering and Concreting MOYAN SCHOOL SIDE
9
BEAM/SLAB RAILWAY SPAN
10
HR/FP/KERB CALICUT SIDE
0.00%
11
HR/FP/KERB NH SIDE
12
HR/FP/KERB RAILWAY SPAN
13
BC/PAINTING
Note: Progress review done based on the revised Program (rev-01)
Availability of Labours
Date
Barbenders
Mechanics/Electricains
Helpers
Ret. Wall work
06-04-2011
23
06-05-2011
06-06-2011
06-07-2011
06-08-2011
06-09-2011
-
06-10-2011
Material Stocking Status
Required
Available
Fine aggregate {m³}
Cement(bag)
400
1150
Steel inT
134
Coarse Aggreagate (m3)
36
Utility shifting
Utilities to be shifted
BSNL
KSEB
Done
KWA
Others