Untitled Document
Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
7886165
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Weekly Reports
Project Graph
weekly progress as on 12.4.2013
Progress Report For Koilandy ROB for the week ending on 12-04-2013
Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance work up to last week
Cumulative delay in Qty up to last week
Work planned during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work Planned for next week
Remarks
1
PILE Muthambi side
27
27
0
0
0
0
0
0
Completed
2
PILE Thamarassery side
33
33
0
0
0
0
0
0
Completed
3
PILE NH SIDE
33
33
0
0
0
0
0
0
Completed
4
PILE CAP Muthambi SIDE
9
9
0
0
0
0
0
0
Completed
5
PILE CAP Thamarassery SIDE
11
11
0
0
0
0
0
0
Completed
6
PILE CAP NH SIDE
10
10
0
0
0
0
0
0
Completed
7
PIER Muthambi SIDE
9
9
0
0
0
0
0
0
Completed
8
PIER Thamarassery SIDE
11
11
0
0
0
0
0
0
Completed
9
PIER NH SIDE
10
10
0
0
0
0
0
0
Completed
10
PIER CAP Muthambi SIDE
9
9
0
0
0
0
0
0
Completed
11
PIER CAP Thamarassery SIDE
11
11
0
0
0
0
0
0
Completed
12
PIER CAP NH SIDE
10
10
0
0
0
0
0
0
Completed
13
RE/R WALL Muthambi side
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
14
RE/R WALL Thamarassery side SIDE
100%
97%
3%
0
3.00%
3.00%
0
0.00%
Completed
15
RE/R WALL NH SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
completed.
16
BEAM/SLAB Muthambi SIDE
8
8
0
0
0
0
0
0
Completed
17
BEAM/SLAB Thamarassery SIDE
10
10
0
0
0
0
0
0
Completed
18
BEAM/SLAB NH SIDE
11
11
0
0
0
0
0
0
Completed
19
HR/FP/KERB Muthambi SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
20
HR/FP/KERB thamarassery SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
21
HR/FP/KERB NH SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
22
PAINTING
100%
95%
5%
0
5.00%
3.00%
0.02
2.00%
in progress. Only few touching works in balance
23
Mastic Work
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
23
Utility shifting
0
KSEB utility shifting started. Only 1 post remaining to shift
Click here to view Previous Reports
Weekly progress report as on 12-04-2013
Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance work up to last week
Cumulative delay in Qty up to last week
Work planned during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work Planned for next week
No of days remaining for completion as per the weekly plan
Remarks
1
PILE Muthambi side
27
27
0
0
0
0
0
0
Completed
2
PILE Thamarassery side
33
33
0
0
0
0
0
0
Completed
3
PILE NH SIDE
33
33
0
0
0
0
0
0
Completed
4
PILE CAP Muthambi SIDE
9
9
0
0
0
0
0
0
Completed
5
PILE CAP Thamarassery SIDE
11
11
0
0
0
0
0
0
Completed
6
PILE CAP NH SIDE
10
10
0
0
0
0
0
0
Completed
7
PIER Muthambi SIDE
9
9
0
0
0
0
0
0
Completed
8
PIER Thamarassery SIDE
11
11
0
0
0
0
0
0
Completed
9
PIER NH SIDE
10
10
0
0
0
0
0
0
Completed
10
PIER CAP Muthambi SIDE
9
9
0
0
0
0
0
0
Completed
11
PIER CAP Thamarassery SIDE
11
11
0
0
0
0
0
0
Completed
12
PIER CAP NH SIDE
10
10
0
0
0
0
0
0
Completed
13
RE/R WALL Muthambi side
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
14
RE/R WALL Thamarassery side SIDE
100%
97%
3%
0
3.00%
3.00%
0
0.00%
Completed
15
RE/R WALL NH SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
completed.
16
BEAM/SLAB Muthambi SIDE
8
8
0
0
0
0
0
0
Completed
17
BEAM/SLAB Thamarassery SIDE
10
10
0
0
0
0
0
0
Completed
18
BEAM/SLAB NH SIDE
11
11
0
0
0
0
0
0
Completed
19
HR/FP/KERB Muthambi SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
20
HR/FP/KERB thamarassery SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
21
HR/FP/KERB NH SIDE
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
22
PAINTING
100%
95%
5%
0
5.00%
3.00%
0.02
2.00%
in progress. Only few touching works in balance
23
Mastic Work
100%
100%
0%
0
0.00%
0.00%
0
0.00%
Completed
23
Utility shifting
0
KSEB utility shifting started. Only 1 post remaining to shift
Availbility of Men
Date
06-04-13
07-04-13
08-04-13
09-04-13
10-04-13
11-04-13
12-04-13
Nof labours
41
31
33
38
36
36
35
Material Stocking Status
Required
Available
Remarks
Coarse Aggreagate (m3)
40
45
Fine Aggreagate(m3)
30
25
Cement(bag)
250
250
Steel(MT)
5
15
Utility shifting
Utilities to be shifted
Status
Remarks
BSNL
KSEB
KWA
Others
Click here to view Previous Reports
AP3 SIDE