1 |
Date of Notice To Proceed |
June 18th 2010 |
2 |
Target date for Completion |
Feb 28th 2013 |
3 |
Name of Project Management Consultant |
KITCO Ltd |
4 |
Name of Contractor |
RDS |
5 |
Total length of bridge including Railway portion |
1013.247 m |
6 |
Length of Railway Portion (Not within the scope of RBDCK) |
32.4m |
7 |
Length of Approach portion towards NH |
338.8m |
8 |
Length of Approach portion towards Balucherry |
461.3m |
9 |
Length of approach portion towards Muthambi |
213.147 |
10 |
Slope of ROB towards NH |
1 in 20 |
11 |
Slope of ROB towards Baluchery |
1 in 30 |
12 |
Slope of ROB towards Muthambi |
1 in 25 |
13 |
Width of carriage way |
7.5 m |
14 |
Foot path |
Nil |
15 |
Total width of bridge including crash barriers |
8.5m |
16 |
Estimate value of work |
19.25 crores |
17 |
Period of completion |
12 months |
18 |
Present Status |
Work completed and ROB inaugrated on 20th April 2013 |