   10.8.2010
    

ROB at Bakel

PROGRESS OF ROB WORK AS ON 31.7.2010

 

Work Planned upto 31/7/2010 Completed / Progress Remarks
Span on Kasargod side    
Concreating Beam and Slab Completed  
Hand rail casting In progress  
Span on Kannur side    
Staging Work Progress Road Blocked on 24-07-2010
 