Si No
Activity Description
Total Quantity
Cumulative progress uptolast week
Balance work up to last week
Cumulative delay in Qty up to this week
Work planned during the week
Actual work done during the week
Work Planned for next week
Remarks
1
PILE RAILWAY SPAN
20
0
2
PILE CAP RAILWAY SPAN
4
3
PIER RAILWAY SPAN
PIER CAP CALICUT SIDE
10
5
PIER CAP NH SIDE
11
6
PIER CAP RAILWAY SPAN
7
RE/R WALL CALICUT SIDE
100%
0.00%
8
RE/R WALL NH SIDE
17.00%
83%
3.00%
9
BEAM/SLAB Staging CALICUT SIDE
BEAM/SLAB Bar bending and Fixing CALICUT SIDE
BEAM/SLAB Shuttering and Concreting Calicut SIDE
12
BEAM/SLAB Staging NH SIDE
13
BEAM/SLAB Bar bending and Fixing NH SIDE
14
BEAM/SLAB Shuttering and Concreting NH SIDE
0.5
P17-P16 girder concrete completed
15
BEAM/SLAB RAILWAY SPAN
16
HR/FP/KERB CALICUT SIDE
17
HR/FP/KERB NH SIDE
18
HR/FP/KERB RAILWAY SPAN
19
BC/PAINTING
Note: Progress review done based on the revised Program (rev-01)