Prevoius Weekly Reports

   progress graph as on 10.6.2011
    

 

 

Progress Report For Pulianam  ROB for the week ending on 10.6.2011
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks
1 Pile towards NH side 26 10 16  nil 4 2 0 4 Heavy rain
2 Pile towards Puliyanam side 18 0 0 nil 0 0 0  

 

 

SlNo Utilities Activities Date  Status  Remarks
1 KWA Joint Inspection with AE,KWA,Angamali 17.3.2011 DD submitted  shifting in progress
2 BSNL Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate to be received  Shifting in progress
3 KSEB Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 DD submitted Shifting completed
4   Joint Inspection with AE,KSEB,Angamali 8.4.2011 DD submitted   Shifting completed
5 KWA Joint Inspection with AE,Project division,KWA,Aluva  8.4.2011 DD submitted  shifting completed
 
Back
 
    
R.O.B AT PULIYANAM .PILE A2

    
    
PILING WORK IN PROGRESS

    
    
DRAIN WORK TOWARDS NH SIDE IN PROGRESS

    
    
PILE CONCRETING AT P10 C

    
 
 
 

 

 

 

 

 

 

 