Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053336
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 10.6.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 09-06-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE (A)PLRVTM SIDE 31 28 0 0 0 0 0 0   KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS
2 PILE(R) PLRVTM SIDE 6 0 0 0 0 0 0 0  
3 PILE (A)VYTLA SIDE 40 0 0 0 0 0 0 0  
4 PILE(R) VYTLA SIDE 6 0 0 0 0 0 0 0  
5 PILE CAP(A) PLRVTM SIDE 8 0 0 0 1 0 1 2  
6 PILE(R) PLRVTM SIDE 1 0 0 0 0 0 0 0  
7 PILE (A)VYTLA SIDE 9 0 0 0 0 0 0 0  
8 PILE(R) VYTLA SIDE 1 0 0 0 0 0 0 0  
9 RE WALL PANEL 370 42 0 0 42 43 0 42    
      HEAVY RAIN AFFECTING THE PROGRESS OF WORK FROM MAY END    

 

KWA

Joint Inspection with Axe and AE,KWA,Pallimukku

21.2.2011

DDsubmitted to EE,KWA on 9.5.2011,

(KWA Tender due date for the shifting work  is on 16.6.2011)

Joint Inspection with AE,AXE and EE KWA

2.4.2011

BSNL

Joint Inspection with DE, BSNL,Palarivattom

23.3.2011

DE, informed that there is no BSNL cable to be  removed

Joint Inspection with SDE,BSNL,Vytilla

11.4.2011

Estimate is to be received

BPCL

Joint Inspection with BPCL

24.3.2011

Span RP1-P9 changed

KSEB 

Joint Inspection with Sub Engineer, KSEB

23.3.2011

Shifting isin progress

Joint Inspection with AE,KSEB,Vyttilla

11.4.2011 

 
Back
 
    
SETTING OUT OF PILE CAP

    
    
DEMOLISHING OF COMPONUD WALL IN THE ACQUIRED LAND

    
    
DEMOLISHING STRUCTURES IN ACQUIRED LAND

    
    
REINFORCEMENT PALCING PILE CAP P15 9.6.2011

    
 
    
P15 PILE CAP PIT 6.6.2011

    
    
RE WALL PANELS STACKED FOR CURING 4.6.2011

      
 

 

 

 

 

 

 

 

Untitled Document