Prevoius Weekly Reports

   weekly progress as on 3.6.2011
    
Progress Report For Palakkad Sultanpet ROB for the week ending on 03-062011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
  PCC for RAFT MOYAN SIDE 1 0 1 0 0 0 0 1    
2 PCC for RAFT PALAKKAD SCHOOL SIDE 3 2 1 1 1 0 0 0    
4 RAFT PALAKKAD SIDE 1 1 0 0 0 0 0 0    
5 RAFT MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
7 PIER PALAKKAD SIDE 1 1 0 0 0 0 0 0    
8 PIER MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
10 PIER CAP PALAKKAD SIDE 1 1 0 0 0 0 0 0    
11 PIER CAP MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
13 RE/R WALL PALAKKAD  SIDE 100% 60% 40% 0 0.00% 0.00% 0.00% 0.00%    
14 RE/R WALL MOYAN SCHOOL SIDE 100% 15% 85% 0 0.00% 0.00% 0.00% 0.00%    
15 BEAM/SLAB  Staging Palakad  SIDE 2 1 1 0 0 0 0 1    
16 BEAM/SLAB  Bar bending and Fixing Palakad  SIDE 2 1 1 0 0 0 0 1    
17 BEAM/SLAB  Shuttering  and Concreting Palakad SIDE 2 0 2 0 0 1 0 o    
18 BEAM/SLAB  Staging Moyan schoolSIDE 4 4 0 0 0 0 0 1    
19 BEAM/SLAB  Bar bending and Fixing Moyan school SIDE 4 4 0 0 0 0 0 1    
20 BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE 4 4 0 0 0 0 0 1    
16 BEAM/SLAB PALAKKAD  SIDE 2 0 2 0 0 1 0 0    
17 BEAM/SLAB MOYAN SCHOOL SIDE 4 4 0 0 0 0 1 1    
18 BEAM/SLAB RAILWAY SPAN 7 0 7 0 0 0 1 0    
19 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
  Note: Progress review done based on the revised Program (rev-01)              
                       
                       
  ROB Sulthanpet, Palakkad                    
  Date Barbenders Mechanics/Electricains Helpers Ret. Wall work            
  5/28/2011 23 5 13 7            
  5/29/2011 23 5 13 5            
  5/30/2011 23 5 13 7            
  5/31/2011 23 5 13 11            
  6/1/2011 23 5 13 11            
  6/2/2011 - 5 3 -            
  6/3/2011 23 5 13 11            
                       
                       
  Material Stocking Status                
    Required Available                
  Fine aggregate {m³} 3 8                
  Cement(bag) 150 1268                
  Steel inT 4 134                
  Coarse Aggreagate (m3)  6  36                
                       
  Utility shifting                  
  Utilities to be shifted   Remarks                
  BSNL                    
  KSEB Done                  
  KWA Done                  
  Others                    
 
Back
 
    
CASTING OF RET WALL (03.06.2011)

    
    
APPROACH FILLING (03.06.2011)

    
    
P1-P2 SLAB CASTING (30.05.2011)

    
    
CONCRETE WORK (30.05.2011)

    
 
    
BARBENDING OF BOWSTRING (30.05.2011)

    
    
APPROACH FILLING (30.05.2011)

      
 

 

 

 

 

 

 

 