Progress Report For Palakkad Sultanpet ROB for the week ending on 03-062011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
|
PCC for RAFT MOYAN SIDE |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
|
|
2 |
PCC for RAFT PALAKKAD SCHOOL SIDE |
3 |
2 |
1 |
1 |
1 |
0 |
0 |
0 |
|
|
4 |
RAFT PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
5 |
RAFT MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
7 |
PIER PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
8 |
PIER MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
10 |
PIER CAP PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
11 |
PIER CAP MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
13 |
RE/R WALL PALAKKAD SIDE |
100% |
60% |
40% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
14 |
RE/R WALL MOYAN SCHOOL SIDE |
100% |
15% |
85% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
15 |
BEAM/SLAB Staging Palakad SIDE |
2 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
|
|
16 |
BEAM/SLAB Bar bending and Fixing Palakad SIDE |
2 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
|
|
17 |
BEAM/SLAB Shuttering and Concreting Palakad SIDE |
2 |
0 |
2 |
0 |
0 |
1 |
0 |
o |
|
|
18 |
BEAM/SLAB Staging Moyan schoolSIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
19 |
BEAM/SLAB Bar bending and Fixing Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
20 |
BEAM/SLAB Shuttering and Concreting Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
16 |
BEAM/SLAB PALAKKAD SIDE |
2 |
0 |
2 |
0 |
0 |
1 |
0 |
0 |
|
|
17 |
BEAM/SLAB MOYAN SCHOOL SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
1 |
1 |
|
|
18 |
BEAM/SLAB RAILWAY SPAN |
7 |
0 |
7 |
0 |
0 |
0 |
1 |
0 |
|
|
19 |
HR/FP/KERB CALICUT SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
20 |
HR/FP/KERB NH SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
21 |
HR/FP/KERB RAILWAY SPAN |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Progress review done based on the revised Program (rev-01) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ROB Sulthanpet, Palakkad |
|
|
|
|
|
|
|
|
|
|
|
Date |
Barbenders |
Mechanics/Electricains |
Helpers |
Ret. Wall work |
|
|
|
|
|
|
|
5/28/2011 |
23 |
5 |
13 |
7 |
|
|
|
|
|
|
|
5/29/2011 |
23 |
5 |
13 |
5 |
|
|
|
|
|
|
|
5/30/2011 |
23 |
5 |
13 |
7 |
|
|
|
|
|
|
|
5/31/2011 |
23 |
5 |
13 |
11 |
|
|
|
|
|
|
|
6/1/2011 |
23 |
5 |
13 |
11 |
|
|
|
|
|
|
|
6/2/2011 |
- |
5 |
3 |
- |
|
|
|
|
|
|
|
6/3/2011 |
23 |
5 |
13 |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
|
|
|
|
|
|
|
|
|
|
Required |
Available |
|
|
|
|
|
|
|
|
|
Fine aggregate {m³} |
3 |
8 |
|
|
|
|
|
|
|
|
|
Cement(bag) |
150 |
1268 |
|
|
|
|
|
|
|
|
|
Steel inT |
4 |
134 |
|
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
6 |
36 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
|
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
|
|
|
|
|
|
|
|
|
|
|
KSEB |
Done |
|
|
|
|
|
|
|
|
|
|
KWA |
Done |
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|