Prevoius Weekly Reports

   weekly progress as on 3.6.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 3.6.2011
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks
1 Pile towards NH side 26 9 16  nil 4 1 3 4 Heavy rain
2 Pile towards Puliyanam side 18 0 0 nil 0 0 0  

 

SlNo Utilities Activities Date  Status  Remarks
1 KWA Joint Inspection with AE,KWA,Angamali 17.3.2011 DD submitted Pipe lines to be shifted
2 BSNL Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate to be received  
3 KSEB Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 DD submitted Shifting in progress
4   Joint Inspection with AE,KSEB,Angamali 8.4.2011 DD submitted   Shifting in progress 
5 KWA Joint Inspection with AE,Project division,KWA,Aluva 
 
Back
 
    
SOIL COLLAPSING NEAR COMPOUND WALL NEAR A2.

    
    
RIG SETTING AT P10 AND A2 31.5.2011

    
    
BORING IN HEAVY RAIN AT P10 1.6.2011

    
    
BORING AT P10 1.6.2011

    
 
    
BORING AT A2 3.6.2011

      
 

 

 

 

 

 

 

 