   Progress Report as on 03.06.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 03-06-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed    
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 0.00%   10.00% 60 days  
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 5.00%   2.00% 60 days CANAL DIVERSION WORK IS COMPLETED EXCEPT FOR SOME BACKFILLING IN THE OLD CANAL.
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 45 days  
12 BEAM/SLAB M.C SIDE 12 5 7 0 1 0 4 1 97 days beam shuttering work for the span P10-P11 going on.Staging works for the span P8-P9 nearing completion.Deshutering of the span P12-P13 completed and P8-P7 in progress.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 25 days  
14 HR/FP/KERB M.C SIDE 100% 7 93% 0 3.00% 0.00% 0.00% 3.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men                 
Date 28-5-2011 29-5-2011 30-5-2011 31-5-2011   1/6/2011 2/6/2011 3/6/2011
No. of labours 15 15 15 28   28 28 28 

 

Material Stocking Status          
  Required Available Remarks      
Fine aggregate {cft} 500 750        
Cement(bag) 630 840        
Steel inT 11 25 sufficient material available at the site      
Coarse Aggreagate (cft) 400 800        
             
Utility shifting            
Utilities to be shifted   Remarks        
BSNL COMPLETED          
KSEB Already shifted          
KWA Shifted          
Others road diversion work    completed          
  Canal diversion work    completed except some back filling in the old canal.          
 
Back
 
    
BEAM REINFORCEMENT P10-P11 (28.05.2011)

    
    
BEAM SHUTTERING OF SPAN P10-P11 (30.05.2011)

    
    
BEAM REINFORCEMENT COMPLETE OF SPAN P10-P11 (31.05.2011)

    
    
STAGING WORKS OF SPAN P8-P9 IN PROGRESS (01.06.2011)

    
 
    
DESHUTTERING OF BEAM BOTTOM COMPLETE OF SPAN P12-P13 (02.06.2011)

    
    
NEW CANAL AFTER THE DIVERSION WORK ALONG WITH THE ROAD (03.06.2011)

      
 

 

 

 

 

 

 

 