Sl .No |
Activity -Description |
Total Quantity |
Cumulative progress up to this week |
Balance work |
Cumulative delay in weeks afterSpplagmnt |
Work planned during the week |
Actual work done during the last week |
Short fall in the last week |
Work Planned for next week |
No of days remaining for completion as per the weekly plan |
Remarks |
|
|
|
-1 |
-2 |
-3 |
-4 |
-5 |
-6 |
-7 |
|
|
1 |
Re wall towards NH side |
100% |
34 |
66 |
27 |
RR work |
0 |
0 |
0 |
19 |
. |
3 |
Approachspan |
5 |
4 |
1 |
33 |
- |
- |
- |
- |
|
|
4 |
Pier cap |
2no |
1 |
3 |
36 |
0 |
0 |
0 |
0 |
18 |
|
5 |
Pile (Rly) Pulikakadavu side |
4 |
4 |
5 |
55 |
0 |
0 |
0 |
0 |
2 |
|
6 |
Pile (Rly)Nh side |
4 |
4 |
5 |
55 |
0 |
0 |
0 |
0 |
2 |
|
6 |
Piers (Rly) |
2No |
1 |
3 |
46 |
0 |
0 |
0 |
0 |
|
2ndlift of pier concreting at p1 completed |
9 |
R0AD WORK {WBM} towards pulikkakadavu side |
100% |
90% |
0 |
|
|
|
|
|
|
|
10 |
GIRDER(LAND SPAN)P2-P3 span |
3 |
3 |
|
|
1 |
1 |
0 |
0 |
41 |
1ststage stressing over |
11 |
P2-P3 span |
Shuttering of deck slab |
|
|
|
Concreting of deck slab P2-P3 |
shuttering work of the deck slab of P2-P3 in progress |
|
Concreting of deck slab on 10-6-2011 |
|
Heavy rain hampering the work in P2-P3 Span |
12 |
Diaphram wall(P2-P3) |
Reinforcement work completed |
|
|
|
Concreting of end diaphragms |
Concreting of two end diaphragms completed successfully |
|
|
|
Work completed as planned |