Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887439
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 3.6.2011
    

 

Sl .No  Activity -Description  Total Quantity  Cumulative progress up to this week  Balance  work  Cumulative delay in weeks afterSpplagmnt  Work   planned  during the week  Actual work done during the last week  Short fall in the last week   Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
      -1 -2 -3 -4 -5 -6 -7    
1 Re wall towards NH side  100% 34 66 27 RR work  0 0 0  19    .
3 Approachspan 5 4 1 33     
4 Pier cap  2no  1 3 36  0   0   0   0   18    
5 Pile (Rly) Pulikakadavu side  4 4 5 55  0  0   0    0  2  
6 Pile (Rly)Nh side 4 4 5 55 0 0 0 0 2  
6 Piers (Rly) 2No  1 3 46  0   0   0   0    2ndlift of pier concreting  at p1 completed
9 R0AD WORK {WBM} towards pulikkakadavu side 100% 90% 0                  
10 GIRDER(LAND SPAN)P2-P3 span 3 3     1 1 0 0 41 1ststage stressing over
11 P2-P3 span  Shuttering of deck slab       Concreting of deck slab P2-P3  shuttering work of the deck slab of P2-P3 in progress   Concreting  of deck slab on 10-6-2011   Heavy rain hampering the work in P2-P3 Span
12 Diaphram wall(P2-P3) Reinforcement work  completed       Concreting of end diaphragms Concreting of two end diaphragms completed successfully       Work completed as planned 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate(m3)

12

30

Remarks

 

Fine Aggreagate(m3)

 13

 20

 .

 

Cement(bag)

 25

 34

 

 

Steel(MT)

 7

 11

 

 

 

 

 

 

  

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 i

 

  

 

 

Date 28-05-2011 30-5-2011 31-5-2011 1-6-.2011 2-6-2011 3-6-2011
Total 15 16 16 21 21 21 

 

 
Back
 
    
SHUTTERING WORK OF P2-P3 SPAN 3.6.2011

    
    
SHUTTERING WORK OF DECK SLAB P2-P3 SPAN 3.6.2011

    
    
SHUTTERING OF DECK SLAB AT P2-P3-2.6.2011

    
    
RR MASONRY AT P1 LOCATION 2.6.2011

    
 
    
END DIAPHRAGM CONCRETE P2-P3 SPAN 30.5.2011

      
 

 

 

 

 

 

 

 

Untitled Document