Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886313
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Weekly Reports

Graph Project Graph

Weekly Progress Report as on 04.07.2014
 
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 20 1          
7 Expansion Joint 21 18 3   0 0 0 0
8 RC wall - Kuttipuram side 100% 100% 0% - 0% 0% 15% 0%
9 RC wall - Kanjipura side 100% 100% 0%   0% 0% 10% 0%
10 BOX culvert 100% 100% 0%   - - - -
11 CC wall kuttipuram side 100% 100% 0%             - 0% 0% 30% 0%
12 E/W  100% 100% 0%   0% 0% 100% 0%
13 Painting 100% 45% 55%   0% 0%   0%
14 RCC Drain NH Side 100% 100% 0%   0% 0%   0%
15 HR 100% 95% 5%   0% 0% 0% 0%
16 GSB Kuttipuram 100% 70% 30%   0% 0% 20% 0%
17 GSB Kanjippura 100% 100% 0%   0% 0% 70% 0%
18 WMM 100% 90% 10%   5% 5% 35% 5%
19 Approach slab 100% 100% 0%   0% 0% 75% 0%
20 Adjacent span Kanjippura 100% 100% 0%   0% 0% 45% 0%
21 Adjacent span Kuttippuram 100% 20% 80%   15% 5% 10% 35%
 
Click here to view Previous Reports
 
    
WMM IN PROGRESS IN KUTTIPPURAM SIDE

    
    
ADJACENT SPAN STAGING KUTTIPPURAM

      
 

 

 

 

 

 

 

 

Untitled Document