   Weekly Progress report as on 03/06/2011
    

 

Progress Report For Kainatty ROB for the week ending on 03-06-2011
Si No
Activity Description
Total Quantity
Cumulative progress upto last week
Balance  work up to last week
Cumulative delay in Qty up to last week
Work  planned  during the week
Actual work done during the week
Cumulative delay in Qty up to this week
Work  Planned for next week
No of days remaing for completion as per the weekly plan
Remarks
1
PILE KAINATTY  SIDE
18
18
0
0
0
0
0
0
 
 
2
PILE NADAPURAM SIDE
27
27
0
0
0
0
0
0
 
 
3
PILE CAP KAINATTY SIDE
6
4
2
2
2
0
2
2
 
 
4
PILE CAP  NADAPURAM SIDE
9
7
2
2
2
0
2
2
 
 
5
PIER KAINATTY  SIDE
6
4
2
3
3
0
2
2
 
 
6
PIER NADAPURAM SIDE
9
7.2
1.8
3.8
3.8
0
3.8
3.8
 
 
7
PIER CAP KAINATTY  SIDE
6
3
3
6
3
0
3
3
 
 
8
PIER CAP NADAPURAM SIDE
9
5
4
5
4
0
4
4
 
 
11
RE/R WALL KAINATTY  SIDE
100%
23%
77%
0
0.00%
2.00%
0.00%
0.00%
 
 
10
RE/R WALL NADAPURAM SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
 
12
BEAM/SLAB  Staging Kainatty side
6
2
4
3
1
0
2
1
 
 
13
BEAM/SLAB  Bar bending and Fixing Kainatty side
6
2
4
3
1
0
2
1
 
 
14
BEAM/SLAB  Shuttering  and Concreting  Kainatty side
6
0
6
3
0
1
2
1
 
 
15
BEAM/SLAB  Staging Nadapuram side
9
0
9
3
0
0
3
0
 
 
16
BEAM/SLAB  Bar bending and Fixing Nadapuram side
9
0
9
3
0
0
3
1
 
 
17
BEAM/SLAB  Shuttering  and Concreting  Nadapuram side
9
0
9
3
0
0
3
0
 
 
18
BEAM/SLAB KAINATTY  SIDE
6
0
6
0
0
0
0
0
 
 
19
BEAM/SLAB NADAPURAM SIDE
9
0
9
0
0
0
0
0
 
 
20
HR/FP/KERB KAINATTY  SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
 
21
HR/FP/KERB NADAPURAM SIDE
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
 
22
BC/PAINTING
100%
0
100%
0
0.00%
0.00%
0.00%
0.00%
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Note: Progress review done based on the revised Program (rev-01)
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Availbility of Men
 
 
 
 
 
 
 
 
 
 
 
Date
 
28-5-2011
29-5-2011
30-5-2011
31-5-2011
06-01-2011
06-02-2011
06-03-2011
 
 
 
Nof labours
 
40
40
40
40
40
40
40
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Material Stocking Status
Required
Available
Remarks
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Fine Aggreagate(m3)
7
10
 
 
 
 
 
 
 
 
 
Cement(bag)
200
450
 
 
 
 
 
 
 
 
 
Steel(MT)
10
21
 
 
 
 
 
 
 
 
 
Coarse Aggreagate (m3)
15
12
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Utility shifting
Status
Remarks
 
 
 
 
 
 
 
 
 
Utilities to be shifted
shifted
 
 
 
 
 
 
 
 
 
 
BSNL
shifted
 
 
 
 
 
 
 
 
 
 
KSEB
to be shifted
 
 
 
 
 
 
 
 
 
 
KWA
shifted
 
 
 
 
 
 
 
 
 
 
Others
 
 
 
 
 
 
 
 
 
 
 
Back
 
    
PILING IN PROGRESS P 5 (01/06/2011)

    
    
REINFORCEMENT OF PIER CAP P 3 (01/06/2011)

    
    
PILING IN PROGRESS P5 (01/06/2011)

    
    
CONCRETING OF SLAB AP1 - P1 (30.05.2011)

    
 
    
SLAB REINFORCEMENT (28.05.2011)

    
    
NEWLY LAID KWA WATER PIPE LINES (27.05.2011)

      
 

 

 

 

 

 

 

 