Prevoius Weekly Reports

   weekly progress as on 3.6.2011
    

 

Progress Report For Ponnurunni  ROB for the week ending on 3.6.2011

Si No 

Activity Description 

Total Quantity

Cumulative progress upto last week 

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week 

 

Actual work done during the week 

Cumulative delay in Qty up to this week

Work  Planned for next week 

No of days remaing for completion as per the weekly plan

Remarks 

1

Pile towards Palarivattom side

31

28

5

 nil

4

 

4

0

 

25

 

2 Pile towards Vytilla side 40 0 40 nil              
  Shifting of Utilities            

 

 

 

KWA Joint Inspection with Axe and AE,KWA,Pallimukku   DD submitted to EE ,KWA on 9.5.2011
Joint Inspection with AE,AXE and EE KWA 2.4.2011 DD submitted 
BSNL Joint Inspection with DE, BSNL,Palarivattom   Estimate is to be received
Joint Inspection with AE,BSNL 11.4.2011 Estimate is to be received
BPCL Joint Inspection with BPCL 24.3.2011 Span RP1-P9 changed
KSEB  Joint Inspection with Sub Engineer, KSEB 23.3.2011 DD submitted to AE KSEB  
 
Back
 
    
PLATFORM FOR CASTING RE WALL PANELS.

    
    
MOCK UP I GIRDER-2

    
    
DEWATERING OF PILE CAP PIT

    
    
BAR PENDING IN PROGRESS FOR PILE CAP

    
 
 
 

 

 

 

 

 

 

 