Si No
Activity Description
Total Quantity
Cumulative progress uptolast week
Balance work up to last week
Cumulative delay in Qty up to this week
Work planned during the week
Actual work done during the week
Work Planned for next week
Remarks
1
RE/R WALL PALAKKAD SIDE
100%
60%
40%
0
2.00%
2
RE/R WALL MOYAN SCHOOL SIDE
15%
85%
3.00%
3
BEAM/SLAB Staging PALAKKAD SIDE
4
BEAM/SLAB Bar bending and Fixing PALAKKAD SIDE
5
BEAM/SLAB Bar Shuttering And Concreting PALAKKAD SIDE
6
BEAM/SLAB Staging MOYAN SCHOOL SIDE
7
BEAM/SLAB Bar bending And Fixing MOYAN SCHOOL SIDE
8
BEAM/SLAB Shuttering and Concreting MOYAN SCHOOL SIDE
9
BEAM/SLAB RAILWAY SPAN
10
HR/FP/KERB CALICUT SIDE
0.00%
11
HR/FP/KERB NH SIDE
12
HR/FP/KERB RAILWAY SPAN
13
BC/PAINTING
Note: Progress review done based on the revised Program (rev-01)
Date
Barbenders
Mechanics/Electricains
Helpers
Ret. Wall work
21-05-2011
23
22-05-2011
15
-
23-05-2011
24-05-2011
25-05-2011
26-05-2011
27-05-2011
Material Stocking Status
Required
Available
Fine aggregate {m³}
Cement(bag)
350
1715
Steel inT
140
Coarse Aggreagate (m3)
40
Utility shifting
Utilities to be shifted
BSNL
KSEB
Done
KWA
Others