Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888134
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 27.5.2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress uptolast week

Balance  work up to last week

Cumulative delay in Qty up to  this week

Work  planned    during the week

Actual work done during the week

Work  Planned for next week

Remarks

1

RE/R WALL PALAKKAD  SIDE

100%

60%

40%

0

2.00%

2.00%

2.00%

 

2

RE/R WALL MOYAN SCHOOL SIDE

100%

15%

85%

0

3.00%

3.00%

3.00%

 

3

BEAM/SLAB  Staging  PALAKKAD  SIDE

2

0

2

1

1

1

0

 

4

BEAM/SLAB  Bar bending and Fixing PALAKKAD  SIDE

2

0

2

1

1

1

0

 

5

BEAM/SLAB  Bar Shuttering And Concreting PALAKKAD  SIDE

2

0

2

1

1

1

1

 

6

BEAM/SLAB  Staging MOYAN SCHOOL SIDE

5

4

1

0

0

0

0

 

7

BEAM/SLAB  Bar bending And Fixing MOYAN SCHOOL SIDE

5

4

1

0

0

0

0

 

8

BEAM/SLAB  Shuttering and Concreting MOYAN SCHOOL SIDE

5

4

1

0

0

0

0

 

9

BEAM/SLAB RAILWAY SPAN

7

0

7

5

0

0

0

 

10

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

 

11

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

 

12

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

 

13

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

 

 

Note: Progress review done based on the revised Program (rev-01)

 

 

 

 

Date

Barbenders

Mechanics/Electricains

Helpers

Ret. Wall work

 

21-05-2011

23

5

13

7

 

22-05-2011

15

5

13

-

 

23-05-2011

23

5

13

7

 

24-05-2011

23

5

13

7

 

25-05-2011

23

5

13

7

 

26-05-2011

23

5

13

7

 

27-05-2011

23

5

13

7

 

 

 

 

 

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

Required

Available

 

 

 

Fine aggregate {m³}

5

 5

 

 

 

Cement(bag)

350

1715

 

 

 

Steel inT

8

140

 

 

 

Coarse Aggreagate (m3)

 8

 40

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

 

Remarks

 

 

 

BSNL

 

 

 

 

 

KSEB

Done

 

 

 

 

KWA

Done

 

 

 

 

Others

 

 

 

 

 

 
Back
 
    
P1-P2 DECKSLAB (27.05.2011)

    
    
PALAKKAD SIDE RET WALL (27.05.2011)

    
    
SHUTTERING WORKS OF RET WALL AT MOYENS SIDE (27.05.2011)

    
    
CROSS BEAM OF BOWSTRING (25.05.2011)

    
 
    
CASTING OF P1-P2 GIRDER (25.05.2011)

    
    
TEMPORARY DIVERSION ROAD (25.05.2011)

      
 

 

 

 

 

 

 

 