Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888376
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 27.5.2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress uptolast week

Balance  work up to last week

Cumulative delay in Qty up to this week

Work  planned during the week

Actual work done during the week

Work  Planned for next week

Remarks

1

PILE RAILWAY SPAN

20

0

20

20

0

0

0

 

2

PILE CAP RAILWAY SPAN

4

0

4

4

2

0

0

 

3

PIER RAILWAY SPAN

4

0

4

4

0

0

0

 

4

PIER CAP CALICUT  SIDE

10

10

7

3

3

3

3

 

5

PIER CAP NH SIDE

11

11

0

0

0

0

0

 

6

PIER CAP RAILWAY SPAN

4

0

4

4

0

0

0

 

7

RE/R WALL  CALICUT  SIDE

100%

0.00%

100%

0

0.00%

0.00%

0.00%

 

8

RE/R WALL  NH SIDE

100%

17.00%

83%

0

0.00%

3.00%

0.00%

 

9

BEAM/SLAB  Staging CALICUT  SIDE

10

3

7

1

0

0

1

 

10

BEAM/SLAB  Bar bending and Fixing CALICUT  SIDE

10

2

7

1

1

1

0

 

11

BEAM/SLAB  Shuttering  and Concreting  Calicut SIDE

10

2

7

1

1

0.5

0.5

 P2-P3 girder concrete completed

12

BEAM/SLAB  Staging NH SIDE

11

3

8

0

1

1

0

 

13

BEAM/SLAB  Bar bending and Fixing NH  SIDE

11

3

8

0

1

0

1

 

14

BEAM/SLAB  Shuttering  and Concreting  NH  SIDE

11

3

8

0

0

0

1

 

15

BEAM/SLAB  RAILWAY SPAN

3

0

3

1

0

0

0

 

16

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

 

17

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

 

18

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

 

19

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

 

 

 

 

 

 

 

 

 

 

 

 

Note: Progress review done based on the revised Program (rev-01)

 

 

Availability of Men

 

 

 

 

 

 

 

Date

21/05/11

22/05/11

23/05/11

24/05/11

25/05/11

26/05/11

27/05/11

No of labours

78

78

72

70

85

86

86

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

 

Material

Required

Available

 

 

 

 

 

Coarse Aggreagate (m3)

66

45

 

 

 

 

 

Fine Aggreagate(m3)

44

30

 

 

 

 

 

Cement(bag)

584

30

 

 

 

 

 

Steel(MT)

13

153

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

 

 

 

BSNL

nil

 

 

 

 

 

 

KSEB

nil

 

 

 

 

 

 

KWA

nil

 

 

 

 

 

 

Others

nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
RBDCK SITE INSPECTION (27.05.2011)

    
    
P1-P2 GIRDER CONCRETING(25.05.2011)

    
    
RETAINING WALL CONCRETING (25.05.2011)

    
    
P17-P16 GIRDER REINFORCEMENT WORK (24.05.2011)

    
 
    
P2-P3 GIRDER SHUTTERING 24.05.2011)

      
 

 

 

 

 

 

 

 

Untitled Document