Work Planned upto 17/7/2010 |
Completed / Progress |
Remarks |
P3-P4 Span |
|
Road Blocked for P3-P4 span work. |
Concreting of Slab & Stressing |
Completed |
|
Approval of GAD by railways (Railway Portion) |
Approved |
Approved on 1-5-10 |
Preparation of Design and Drawing |
In progress |
|
Under Pass Wall concreting 3rd lift & slab |
Completed |
|