   Weekly Progress as on 27.05.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 27-05-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed    
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 2.00%   10.00%  67 days bottom reinforcement of foundation of RCC retaining wall in progress.
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 4.00%   5.00% 67 days canal diversion work completed upto 30%
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 51 days  
12 BEAM/SLAB M.C SIDE 12 4 8 0 1 1 4 1 104 days CONCRETING of beam and deck slab of the span P8-P7 completed.Beam reinforcement of the span P10-P11 in progress.Staging works of the span P8-P9 in progress.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 25 days  
14 HR/FP/KERB M.C SIDE 100% 7 93% 0 3.00% 0.00% 0.00% 3.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
                        

 

Availbility of Men                   
Date 21-5-2011 22-5-2011 23-5-2011 24-5-2011   25-5-2011 26-5-201127-5-2011 27-5-2011  
Nof labours 55 35 35 35   35 12 15   

 

Material Stocking Status            
  Required Available Remarks      
Fine aggregate {cft} 500 600        
Cement(bag) 630 1045        
Steel inT 11 29 sufficient material available at the site      
Coarse Aggreagate (cft) 400 800        

 

Utility shifting        
Utilities to be shifted   Remarks    
BSNL  CABLE SHIFTED      
KSEB already shifted      
KWA SHIFTED      
Others road diversion work  completed        
 
Back
 
    
CONCRETING OF BEAM AND DECK SLAB OF SPAN P8 - P7 (21.05.2011)

    
    
STAGING WORK OF SPAN P8-P9 (23.05.2011)

    
    
CANAL DIVERSION AT MEDICAL COLLEGE SIDE (24.05.2011)

    
    
REINFORCEMENT WORK OF RC WALL AT SHORNUR SIDE (24.05.2011)

    
 
    
CANAL DIVERSION WORK AT MEDICAL COLLEGE SIDE (25.05.2011)

    
    
STAGING AND SHUTTERING OF SPAN P10 - P11 (25.05.2011)

    
    
REINFORCEMENT WORK OF RC WALL AT SHORNUR SIDE (26.05.2011)

    
 
    
REINFORCEMENT WORK OF THE SPAN P10-P11 (27.05.2011)

      
 

 

 

 

 

 

 

 