Prevoius Weekly Reports

   weekly progress 27.5.2011
    

 

 

 

SlNo Utilities Activities Date  Status  Remarks
1 KWA Joint Inspection with AE,KWA,Angamali 17.3.2011 DD submitted Pipe lines to be shifted
2 BSNL Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate to be received  
3 KSEB Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 DD submitted Electric  lines to be shifted
4   Joint Inspection with AE,KSEB,Angamali 8.4.2011 DD submitted   
5 KWA Joint Inspection with AE,Project division,KWA,Aluva 1.4.2011 DD submitted Pipe lines to be shifted 

 

  

  1. Excavation for drain 15m completed. (NH Side)
  2. PCC for drain 30.0m completed. (NH side )
  3. Base slab of drain 35m completed. (Puliyanam side)
  4. Pile concreting 4Nos. (P7c, P8b& Pa)completed 
 
Back
 
    
PILE CONCRETING AT P8

      
 

 

 

 

 

 

 

 