   Weekly Progress as on 20.05.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 20-05-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed         
2 PILE M.C SIDE 36 36       Completed         
3 PILE CAP SHORNUR SIDE 3 3       Completed         
4 PILE CAP  M.C SIDE 12 12       Completed         
5 PIER SHORNUR  SIDE 3 3       Completed         
6 PIER M.C SIDE 12 12       Completed         
7 PIER CAP SHORNUR  SIDE 3 3       Completed         
8 PIER CAP M.C SIDE 12 12       Completed         
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 0.00% 96.00% 10.00%  74 days  
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 0.00% 53.00% 5.00% 74 days  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 58 days  
12 BEAM/SLAB M.C SIDE 12 4 8 0 1 0 4 1 111 days Slab reinforcement and shuttering of span P8-P7 in progress.Deshuttering of Beam bottom of span P9-P10 completed.Staging works of span P10-P11 completed. Deshuttering works of span P12-P13 in progress.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 32 days  
14 HR/FP/KERB M.C SIDE 100% 7 93% 0 0.00% 3.00% 0.00% 3.00%   kerb concreting of span P12-P13 completed.
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                     

 

 

Availbility of Men                                 
Date 14-5-'11 15-5-2011 16-5-2011 17-5-2011   18-5-2011 19-5-2011 20-5-2011                
Nof labours 50 53 35 35   35 35 35                
                                 
Material Stocking Status                                
  Required Available Remarks                          
Fine aggregate {cft} 400 800                            
Cement(bag) 630 1086                            
Steel inT 11 40 sufficient material available at the site                          
Coarse Aggreagate (cft) 400 800                            
                                 
Utility shifting                                
Utilities to be shifted   Remarks                            
BSNL  CABLE REROUTED The BSNL has laid the cables at the site and  they have  connected  the cables to the the joints. no hindrance for canal deviation work due to BSNL                            
KSEB already shifted                              
KWA  hindrance The KWA has laid the new PVC cables and connected them .Therefore no hindrance from KWA                            
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.{earthwork excavation }for sectioning}started  today COMPLETED  The bituminous macadum layer has been laid .(road tarring work completed)             k completed.CANAL DIVERSION WORK COMMENCED ON 17-5-2011      

 

 
Back
 
    
BEAM SHUTTRING OF SPAN P8-P7 (16.05.2011)

    
    
CANAL DIVERSION WORK USING HITACHI (19.05.2011)

    
    
CANAL DIVERSION WORK

    
    
COMMENCEMENT OF CANAL DIVERSION WORK (17.05.2011)

    
 
    
KERB CONCRETING SPAN P12-P13 (18.05.2011)

    
    
SLAB REINFORCEMENT OF SPAN P8-P7 (20.05.2011)

    
    
STAGING WORK OF SPAN P10-P11 (18.05.2011)

    
 
 
 

 

 

 

 

 

 

 