   27.07.2010
    

ROB at Koratty

PROGRESS OF ROB WORK AS ON 24.07.2010

 

Work Planned upto 24/7/2010 Completed / Progress Remarks
P3-P4 Span   Road under P3-P4 span  opened for traffic.
Concreting of Slab & Stressing Completed  
Approval of GAD by railways (Railway Portion) Approved Approved on 1-5-10
Preparation of Detailed Design and Drawing In progress Foundation and substructure Design submitted. Superstructure drawings not submitted by the contractor
Under Pass  concreting  Completed  
 