Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887346
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   20-05-2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE RAILWAY SPAN

20

0

20

20

0

0

0

0

 

2

PILE CAP RAILWAY SPAN

4

0

4

3

2

0

0

0

 

3

PIER RAILWAY SPAN

4

0

4

3

0

0

3

0

 

4

PIER CAP CALICUT  SIDE

10

10

7

3

3

3

0

3

 

5

PIER CAP NH SIDE

11

11

0

0

0

0

0

0

 

6

PIER CAP RAILWAY SPAN

4

0

4

3

0

0

0

0

 

7

RE/R WALL  CALICUT  SIDE

100%

0.00%

100%

0

0.00%

0.00%

0.00%

0.00%

 

8

RE/R WALL  NH SIDE

100%

17.00%

83%

0

0.00%

3.00%

0.00%

0.00%

 

9

BEAM/SLAB  Staging CALICUT  SIDE

10

2

8

0

0

1

0

1

 

10

BEAM/SLAB  Bar bending and Fixing CALICUT  SIDE

10

1.5

8.5

0

0

1.2

0

1

 

11

BEAM/SLAB  Shuttering  and Concreting  Calicut SIDE

10

1.5

8.5

0

0

0.5

0

0

 

12

BEAM/SLAB  Staging NH SIDE

11

3.75

7.25

5

1

0.25

0

1

 

13

BEAM/SLAB  Bar bending and Fixing NH  SIDE

11

3

8

4

0

0.5

0

1

 

14

BEAM/SLAB  Shuttering  and Concreting  NH  SIDE

11

2.5

8.5

1

0

0.5

0

1

 

15

BEAM/SLAB  RAILWAY SPAN

3

0

3

0

0

0

0

0

 

16

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

17

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

18

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

19

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: Progress review done based on the revised Program (rev-01)

 

 

 

 
Back
 
    
SLAB CONCRETING P18-P17 (19.05.2011)

    
    
GIRDER IN P2-P3 (19.05.2011)

    
    
P9 PIERCAP (17.05.2011)

    
    
EARTH WORK FOR RE WALL (17.05.2011)

    
 
    
RETAINING WALL CONCRETING (16.05.2011)

    
    
SLAB CONCRETING P1-P2 (16.05.2011)

    
    
STAGING P17-P16 (16.05.2011)

    
 
 
 

 

 

 

 

 

 

 