Progress Report For Parappanangadi ROB for the week ending on 13-05-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CALICUT SIDE |
30 |
30 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
2 |
PILE NH SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
3 |
PILE RAILWAY SPAN |
20 |
0 |
20 |
20 |
0 |
0 |
20 |
0 |
|
|
4 |
PILE CAP CALICUT SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
5 |
PILE CAP NH SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
6 |
PILE CAP RAILWAY SPAN |
4 |
0 |
4 |
3 |
2 |
0 |
4 |
4 |
|
|
7 |
PIER CALICUT SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
8 |
PIER NH SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
9 |
PIER RAILWAY SPAN |
4 |
0 |
4 |
3 |
0 |
0 |
4 |
0 |
|
|
10 |
PIER CAP CALICUT SIDE |
10 |
7 |
3 |
3 |
3 |
0 |
3 |
3 |
|
|
11 |
PIER CAP NH SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
12 |
PIER CAP RAILWAY SPAN |
4 |
0 |
4 |
2 |
0 |
0 |
4 |
0 |
|
|
13 |
RE/R WALL CALICUT SIDE |
100% |
0.00% |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
14 |
RE/R WALL NH SIDE |
100% |
15.00% |
85% |
0 |
0.00% |
2.00% |
0.00% |
0.00% |
|
|
15 |
BEAM/SLAB Staging CALICUT SIDE |
10 |
2 |
8 |
0 |
0 |
0 |
0 |
1 |
|
|
16 |
BEAM/SLAB Bar bending and Fixing CALICUT SIDE |
10 |
1.5 |
8.5 |
0 |
0 |
0 |
0 |
1 |
|
|
17 |
BEAM/SLAB Shuttering and Concreting Calicut SIDE |
10 |
1.5 |
8.5 |
0 |
0 |
0 |
0 |
o |
|
|
18 |
BEAM/SLAB Staging NH SIDE |
11 |
3 |
8 |
5 |
1 |
0.75 |
0 |
1 |
|
|
19 |
BEAM/SLAB Bar bending and Fixing NH SIDE |
11 |
2.5 |
8.5 |
4 |
0 |
0.5 |
0 |
1 |
|
|
20 |
BEAM/SLAB Shuttering and Concreting NH SIDE |
11 |
2.5 |
8.5 |
1 |
0 |
0 |
0 |
1 |
|
|
21 |
BEAM/SLAB CALICUT SIDE |
10 |
1 |
9 |
0 |
0 |
0 |
0 |
0 |
|
|
22 |
BEAM/SLAB NH SIDE |
11 |
2 |
9 |
0 |
0 |
0 |
0 |
0 |
|
|
23 |
BEAM/SLAB RAILWAY SPAN |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
24 |
HR/FP/KERB CALICUT SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
25 |
HR/FP/KERB NH SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
26 |
HR/FP/KERB RAILWAY SPAN |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
27 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Progress review done based on the revised Program (rev-01) |
|
|
|
|