   weekly progress as on 13.5.2011
    

 

SlNo Utilities Activities Date  Status  Remarks
1 KWA Joint Inspection with AE,KWA,Angamali 17.3.2011 DD submitted Pipe lines to be shifted
2 BSNL Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate to be received  
3 KSEB Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 DD submitted Electric  lines to be shifted
4   Joint Inspection with AE,KSEB,Angamali 8.4.2011 DD submitted   
5 KWA Joint Inspection with AE,Project division,KWA,Aluva 1.4.2011 DD submitted Pipe lines to be shifted 

work status

Piling started on 05.05.2011

 

 
Back
 
    
DRAIN WORK IN PROGRESS(10.05.2011)

    
    
PILING WORK AT P7(10.05.2011)

    
    
STEEL REINFORCEMENT FOR PILING WORK(10.05.2011)

    
    
PILING AT P7 (07.05.2011)

    
 
    
DRAIN WORK IN PROGRESS(07.05.2011)

    
    
DRAIN WORK IN PROGRESS(07.05.2011)

      
 

 

 

 

 

 

 

 