Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053537
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 13.5.2011
    

 

Progress Report For Ponnurunni  ROB for the week ending on 06.05.2011

Si No 

Activity Description 

Total Quantity

Cumulative progress upto last week 

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week 

Actual work done during the week 

Cumulative delay in Qty up to this week

Work  Planned for next week 

No of days remaing for completion as per the weekly plan

Remarks 

1

PILE towards Palarivattom side

31

28

5

 nil

4

4

0

Piling chipping and PCC for pile cap

25

 

2

PILE towards vytilla side

40

0

 40

 nil

  

  Shifting of Utilities          

 

KWA Joint Inspection with Axe and AE,KWA,Pallimukku   DD submitted
Joint Inspection with AE,AXE and EE KWA 2.4.2011 DD submitted 
BSNL Joint Inspection with DE, BSNL,Palarivattom   Estimate is to be received
Joint Inspection with AE,BSNL 11.4.2011 Estimate is to be received
BPCL Joint Inspection with BPCL 24.3.2011 Span RP1-P9 changed
KSEB  Joint Inspection with Sub Engineer, KSEB 23.3.2011 DD submitted to Ae KSEB
     

 

 
Back
 
    
-PILE CHIPPING AT P14 7-5-2011-

    
    
RIG SHIFTED TO P2 VYTILLA SIDE 9-5-2011--

    
    
PILE CAP EXCAVATION AT P1110-5-2011--

    
    
BENTONITE TANK AT A111-5-2011--

    
 
    
ARRANGEMENT FOR PILE LOAD TEST--P14 P4 11-5-2011--

    
    
PILE CHIPPING AT P16 12-5-2011--

    
    
SHUTTERING MATERIALS STACKED AT SITE 13-5-2011--

    
 
 
 

 

 

 

 

 

 

 

Untitled Document