   Progress Report as on 06.05.2011
    

 

Progress Report For Kainatty ROB for the week ending on 06-05-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 3 3 3 3 0 3 3    
4 PILE CAP  NADAPURAM SIDE 9 7 2 2 2 0 2 2    
5 PIER KAINATTY  SIDE 6 3 3 3 3 0 3 3    
6 PIER NADAPURAM SIDE 9 5.2 3.8 3.8 3.8 2 1.8 1.8    
7 PIER CAP KAINATTY  SIDE 6 3 3 6 3 0 3 3    
8 PIER CAP NADAPURAM SIDE 9 4 5 5 4 0 5 4    
11 RE/R WALL KAINATTY  SIDE 100% 23% 77% 0 0.00% 2.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 1 5 0 1 1 0 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 1 5 0 1 1 0 1    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 0 6 0 0 0 0 1    
15 BEAM/SLAB  Staging Nadapuram side 9 0 9 0 0 0 0 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 0 9 0 0 0 0 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 0 9 1 0 0 0 0    
18 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 0 0 0    
19 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men               
Date   30-4-'11 05-02-2011 05-03-2011 05-04-2011 05-05-2011 05-06-2011
Nof labours   41 41 41 41 41 41 

 

Material Stocking Status Required Available Remarks  
         
Fine Aggreagate(m3) 25 6    
Cement(bag) 1000 350    
Steel(MT) 25 19    
Coarse Aggreagate (m3) 25 20     

 

 

Utility shifting Status Remarks    
Utilities to be shifted shifted      
BSNL shifted      
KSEB to be shifted      
KWA        
Others         

 

 