Prevoius Weekly Reports

   Weekly report as on 06.05.2011
    
 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaingfor completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

34

66

22

0

0

0

0

 32 days

.

2

RE wall towards Pulikkakadavuside

100%

100

0

40

0

0

0

0

 0

 

3

Approach

 Span

 

5

 

4

1

28

-

-

-

-

 

 

4

Pier cap

4no

1

3

31

 0

 0

 0

 0

 39

 

5

Pile (Rly)pulikakadavuside

4

4

 

0

50

 0

 0

016

 

6

Pile (Rly)Nhside

4

4

0

50

0

0

0

0

09

 

 

6

Piers (Rly)

 

2No

1

3

41

 0

 0

 0

 0

 

 

9

R0AD WORK

{WBM}

100%

80%

 

0

 

 10

 10%

 

 

 

 

WBM  work completed

10

GIRDER

(P2-P3)

3

3

0

30

1

1

0

0

62 days

 

11

 pile cap

2

2

 

 

 

 

 

0

0

 

Kerband hand rail towards Pulikkakadavuside completed 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

15

24

Remarks

 

Fine Aggreagate(m3)

 6

 13

 .

 

Cement(bag)

 12

 25

 

 

Steel(MT)

 3

12

 

 

 

 

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 i

 

  

  

Climate

 

DATE

30-4-2011

02-5-2011

03-5-2011

04-5-2011

05-5-2011

06-05-2011

 

Weather

hot

Hot,rainin the evening

Sunny,rainin the evening

   sunny

gloomy

sunny

 

 

 

LabourDetails 

 

Date

Labours

Pile chipping and  andpile cap

 

Span P2-P3

Beam work

Mechanic and operators

RE wall work

Total

30-4-2011

9

0

10

4

0

23

02-5-2011

8

0

11

4

0

23

03-5-2011

9

0

11

5

0

25

04-5-2011

9

0

11

5

0

25

05-5-.2011

4

0

11

4

0

19

06-5-2011

5

0

13

4

0

22 

 

 
Back
 
    
BITUMEN FOR ROAD WORK AT PULIAKAKADAVU SIDE

    
    
GIRDER REINFORCEMENT IS IN PROGRESS 4.5.2011

    
    
PIER REINFORCEMENT IS IN PROGRESS 2.5.2011

      
 

 

 

 

 

 

 

 