   19-6-2010
    

ROB at Athani

Work Planned upto 12-6-2010
Completed/Progress Remarks
RE wall works Medical College side  Completed Restarted on 12.4.10
PCC for friction slab Completed  
Friction slab concreting In progress  
Hand rail for RE wall In progress  
Road work Completed  
Toll Booth  In progress  
 