Prevoius Weekly Reports

   Weekly report as on 06.05.2011
    
SlNo Utilities Activities Date  Status  Remarks
1 KWA Joint Inspection with AE,KWA,Angamali 17.3.2011 DD submitted Pipe lines to be shifted
2 BSNL Joint Inspection with DE, BSNL,Angamali 17.3.2011 Estimate to be received  
3 KSEB Joint Inspection with Sub Engineer, KSEB,Karukutti 23.3.2011 DD submitted Electric  lines to be shifted
4   Joint Inspection with AE,KSEB,Angamali 8.4.2011 DD submitted   
5 KWA Joint Inspection with AE,Project division,KWA,Aluva 1.4.2011 DD submitted Pipe lines to be shifted 

work status

Piling started on 05.05.2011

 
Back
 
    
ARRANGEMENTS FOR BENTONET TANK

    
    
DRAIN WORK TOWARDS PULIYANAM SIDE IN PROGRESS 3.5.2011

    
    
ARRANGEMENTS FOR BENTONET TANK

    
    
TRIPOD ARRANGEMENTS FOR PILING AT P7 6.5.2011

    
 
    
DRAIN WORK TOWARDS PULIYANAM SIDE IN PROGRESS - 6.5.2011

    
    
ARRANGEMENTS FOR BENTONET TANK

      
 

 

 

 

 

 

 

 