   06/05/2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress uptolast week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned    during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

RE/R WALL PALAKKAD  SIDE

100%

45%

55%

0

5.00%

3.00%

2.00%

5.00%

2

RE/R WALL MOYAN SCHOOL SIDE

100%

12%

88%

0

5.00%

2.00%

3.00%

5.00%

3

BEAM/SLAB  Staging  PALAKKAD  SIDE

2

0

2

0

0

0

0

1

4

BEAM/SLAB  Bar bending and Fixing PALAKKAD  SIDE

2

0

2

0

0

0

0

1

5

BEAM/SLAB  Bar Shuttering And Concreting PALAKKAD  SIDE

2

0

2

0

0

0

0

0

6

BEAM/SLAB  Staging MOYAN SCHOOL SIDE

5

4

1

4

0

0

0

0

7

BEAM/SLAB  Bar bending And Fixing MOYAN SCHOOL SIDE

5

4

2

3

0

0

0

0

8

BEAM/SLAB  Shuttering and Concreting MOYAN SCHOOL SIDE

5

3

2

1

1

1

0

0

9

BEAM/SLAB RAILWAY SPAN

7

0

7

0

0

0

1

0

10

HR/FP/KERB CALICUT  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

11

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

12

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

13

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

Note: Progress review done based on the revised Program (rev-01)

 

 

 

Date

Barbenders

Mechanics/Electricains

Helpers

Ret. Wall work

30-04-2011

27

7

17

14

01-05-2011

27

7

17

14

02-05-2011

27

7

15

22

03-05-2011

27

7

15

18

04-05-2011

27

7

15

16

05-05-2011

27

7

15

12

06-05-2011

27

7

15

12

 

 

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

Required

Available

 

 

Fine aggregate {m³}

10

 14

 

 

Cement(bag)

100

396

 

 

Steel inT

2

80

 

 

Coarse Aggreagate (m3)

 15

 18

 

 

 

 

 

 

 

Utility shifting

 

 

 

Utilities to be shifted

 

Remarks

 

 

BSNL

 

 

 

 

KSEB

Done

 

 

 

KWA

Done

 

 

 

Others

 

 

 

 

 
Back
 
    
SHUTTERING OF BOWSTRING I GIRDER (06.05.2011)

    
    
SHUTTERING WORK OF RET WALL (06.05.2011)

    
    
BOWSTRING CROSS BEAM BARBENDING (06.05.2011)

    
    
BOWSTRING I GIRDER (05.05.2011)

    
 
    
MOYENS SIDE RET WALL EXCAVATION (05.05.2011)

    
    
P7-P8 DECK SLAB CONCRETING (01.05.2011)

    
    
RET WALL BARBENDING (30.04.2011)

    
 
 
 

 

 

 

 

 

 

 