   Weekly report as on 06.05.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 06.05.2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed   pedestal concreting completed 8 locations.P13,P12,P11,P10,P9,AP2,P8,P7. No progress during this week
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 0.00% 86.00% 10.00% 88 days PCC laid for 65 square metre shortage  of labour seriously affecting the progress of the work.in the shornur side approach.No progress during this week
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 0.00% 48.00% 5.00% 88days casting of panels 210no: completed.No progress during this week
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 58 days  
12 BEAM/SLAB M.C SIDE 12 3 9 3 1 1 2 1 125 days Out of 15 No.s of span  4 spans in the M.C side completed…staging and shuttering of 5th span P8-P7 in progress.Deshuttering of the span P12-P13 and P9-P10 in progress.Steelwork for the span P8-P7 in progress. 
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 46 days  
14 HR/FP/KERB M.C SIDE 100% 3 97% 0 3.00% 3.00% 0.00% 1.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

 

Availbility of Men            
Date 30-4-'11 1/5/2011 2/5/2011 3/5/2011 4/5/2011 5/5/2011 6/5/2011
Nof labours 45 40 22 22 22 28 28 

 

 

 

Material Stocking Status

     
  Required Available Remarks
Fine aggregate {cft} 100 540  
Cement(bag) 630 850  
Steel inT 11 15 sufficient material available at the site
Coarse Aggreagate (cft) 400 640   

 

 

 

Utility shifting

 

 

Utilities to be shifted

Remarks

BSNL

BSNL CABLE REROUTED

Shifted

KSEB

already shifted

 

KWA

hindrance - Pipe line

Shifted

Others

road diversion work Bitumenous macadum layer is left to be done.

 

canal diversion work will be started soon after closing of the water flow. 

 
Back
 
    
SHIFTING BSNL TELEPHONE LINE - 30.04.2011

    
    
CONCRETING OF SLAB P12- P13 - 30.04.2011

    
    
STAGING WORK OF THE SPAN P8-P7 - 02.05.2011

    
    
STAGING WORK OF SPAN P8-P7 - 03.05.2011

    
 
    
STAGING & SHUTTERING WORKS OF THE SPAN P8-P7 - 04.05.2011

    
    
KERB CONCRETING OF SLAB - 05.05.2011

    
    
STAGING AND SHUTTERING OF SPAN P8-P7 - 06.05.2011

    
 
 
 

 

 

 

 

 

 

 