Progress Report For Payyannur ROB for the week ending on 29-04-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
1 |
PILE THRIKKARIPUR SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
PILE EZHIMALA SIDE |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
PILE PAYYANNUR SIDE |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
PILE CAP THRIKKARIPUR SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
PILE CAP EZHIMALA SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
6 |
PILE CAP PAYYANNUR SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
9 |
PIER THRIKKARIPUR SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
8 |
PIER EZHIMALA SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
9 |
PIER PAYYANNUR SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
10 |
PIER CAP THRIKKARIPUR SIDE |
11 |
9 |
2 |
2 |
2 |
0 |
2 |
2 |
11 |
PIER CAP EZHIMALA SIDE |
9 |
8 |
1 |
1 |
1 |
0 |
1 |
1 |
12 |
PIER CAP PAYYANNUR SIDE |
9 |
7 |
2 |
2 |
2 |
0 |
2 |
2 |
16 |
RE/R WALL THRIKKARIPUR SIDE |
100% |
45% |
55% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
17 |
RE/R WALL EZHIMALA SIDE |
100% |
45% |
55% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
18 |
RE/R WALL PAYYANNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
100.00% |
0.00% |
19 |
BEAM/SLAB Staging Thrikkaripur side |
9 |
2 |
7 |
0 |
1 |
1 |
3 |
1 |
20 |
BEAM/SLAB Bar bending and Fixing Thrikkaripur side |
9 |
2 |
7 |
0 |
1 |
1 |
3 |
1 |
21 |
BEAM/SLAB Shuttering and Concreting Thrikkaripur side |
9 |
0 |
9 |
0 |
0 |
0 |
3 |
1 |
22 |
BEAM/SLAB Staging Ezhimala side |
8 |
1 |
7 |
0 |
0 |
0 |
0 |
1 |
23 |
BEAM/SLAB Bar bending and Fixing Ezhimala side |
8 |
1 |
7 |
0 |
0 |
0 |
0 |
2 |
24 |
BEAM/SLAB Shuttering and Concreting Ezhimala side |
8 |
0.5 |
7.5 |
0 |
0 |
0 |
0 |
1 |
25 |
BEAM/SLAB Staging Payyanur side |
9 |
2 |
7 |
0 |
0 |
0 |
0 |
1 |
26 |
BEAM/SLAB Bar bending and Fixing Payyanur side |
9 |
1.9 |
7.1 |
0 |
0 |
0.1 |
0 |
1 |
27 |
BEAM/SLAB Shuttering and Concreting Payyanur side |
9 |
1 |
8 |
0 |
0 |
0 |
0 |
|
28 |
BEAM/SLAB THRIKKARIPUR SIDE |
10 |
2 |
8 |
0 |
0 |
0 |
0 |
0 |
29 |
BEAM/SLAB EZHIMALA SIDE |
8 |
0 |
8 |
0 |
0 |
0 |
0 |
0 |
30 |
BEAM/SLAB PAYYANNUR SIDE |
9 |
1 |
8 |
0 |
0 |
0 |
0 |
0 |
31 |
HR/FP/KERB THRIKKARIPUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
32 |
HR/FP/KERB EZHIMALA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
33 |
HR/FP/KERB PAYYANNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
34 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |