   Weekly Progress Report as on 29.04.2011
    
   
Progress Report For Payyannur ROB for the week ending on 29-04-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PILE THRIKKARIPUR  SIDE 33 33 0 0 0 0 0 0
2 PILE EZHIMALA SIDE 27 27 0 0 0 0 0 0
3 PILE PAYYANNUR SIDE 27 27 0 0 0 0 0 0
4 PILE CAP THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0
5 PILE CAP EZHIMALA SIDE 9 9 0 0 0 0 0 0
6 PILE CAP PAYYANNUR SIDE 9 9 0 0 0 0 0 0
9 PIER THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0
8 PIER EZHIMALA SIDE 9 9 0 0 0 0 0 0
9 PIER PAYYANNUR SIDE 9 9 0 0 0 0 0 0
10 PIER CAP THRIKKARIPUR  SIDE 11 9 2 2 2 0 2 2
11 PIER CAP EZHIMALA SIDE 9 8 1 1 1 0 1 1
12 PIER CAP PAYYANNUR SIDE 9 7 2 2 2 0 2 2
16 RE/R WALL THRIKKARIPUR  SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%
17 RE/R WALL EZHIMALA SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%
18 RE/R WALL PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 100.00% 0.00%
19 BEAM/SLAB  Staging Thrikkaripur side 9 2 7 0 1 1 3 1
20 BEAM/SLAB  Bar bending and Fixing Thrikkaripur side  9 2 7 0 1 1 3 1
21 BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side 9 0 9 0 0 0 3 1
22 BEAM/SLAB  Staging Ezhimala side 8 1 7 0 0 0 0 1
23 BEAM/SLAB  Bar bending and Fixing Ezhimala side 8 1 7 0 0 0 0 2
24 BEAM/SLAB  Shuttering  and Concreting  Ezhimala side 8 0.5 7.5 0 0 0 0 1
25 BEAM/SLAB  Staging Payyanur side 9 2 7 0 0 0 0 1
26 BEAM/SLAB  Bar bending and Fixing Payyanur side 9 1.9 7.1 0 0 0.1 0 1
27 BEAM/SLAB  Shuttering  and Concreting Payyanur side 9 1 8 0 0 0 0  
28 BEAM/SLAB THRIKKARIPUR  SIDE 10 2 8 0 0 0 0 0
29 BEAM/SLAB EZHIMALA SIDE 8 0 8 0 0 0 0 0
30 BEAM/SLAB PAYYANNUR SIDE 9 1 8 0 0 0 0 0
31 HR/FP/KERB THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
32 HR/FP/KERB EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
33 HR/FP/KERB PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
34 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%

 

 

Availbility of Men 

           
Date 23-4-'11 24-4-2011 25-4-2011 26-4-2011 27-4-2011 28-4-2011
Nof labours 32 32 32 32 32 32

 

 

Material Stocking Status

     
  Required Available Remarks
Coarse Aggreagate (m3)      
Fine Aggreagate(m3)      
Cement(bag) 600 2400  
Steel(MT) 10 270  

 

 
Back
 
    
P3-P4 GIRDER - 25.04.2011

    
    
ROAD WORK KAVVAYI JUNCTION - 26.04.2011

    
    
SIDE SHUTTER FIRST LOAD - 27.04.2011

    
    
RR MASONRY TRIKARIPUR SIDE - 27.04.2011

    
 
    
RETAINING WALL EZHIMALA - 27.04.2011

    
    
P11-12 GIRDER CONCRETED - 27.04.2011

    
    
SERVICE ROAD EZHIMALA SIDE - 28.04.2011

    
 
    
P18-19 GIRDER SHUTTERING - 28.04.2011

      
 

 

 

 

 

 

 

 