   Weekly report as on 29.04.2011
    
Progress Report For Kainatty ROB for the week ending on 29-04-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 3 3 3 3 0 3 3    
4 PILE CAP  NADAPURAM SIDE 9 7 2 2 2 0 2 2    
5 PIER KAINATTY  SIDE 6 3 3 3 3 0 3 3    
6 PIER NADAPURAM SIDE 9 5.2 3.8 3.8 3.8 0 3.8 3.8    
7 PIER CAP KAINATTY  SIDE 6 3 3 6 3 0 3 3    
8 PIER CAP NADAPURAM SIDE 9 4 5 5 4 0 5 4    
11 RE/R WALL KAINATTY  SIDE 100% 75% 25% 0 0.00% 25.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 1 5 0 1 0 0 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 1 5 0 1 0 0 1    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 0 6 0 0 0 0 1    
15 BEAM/SLAB  Staging Nadapuram side 9 0 9 0 0 0 0 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 0 9 0 0 0 0 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 0 9 1 0 0 0 0    
18 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 0 0 0    
19 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

Availbility of Men 

             
Date   23-4-'11 24-4-2011 25-4-2011 26-4-2011 27-4-2011 28-4-2011
Nof labours   40 40 40 40 40 40 

 

 

Material Stocking Status Required Available Remarks  
         
Fine Aggreagate(m3)        
Cement(bag) 1000 400    
Steel(MT) 25 20    
Coarse Aggreagate (m3)         

 

 

Utility shifting Status Remarks    
Utilities to be shifted shifted      
BSNL shifted      
KSEB to be shifted      
KWA        
Others         
 
Back
 
    
RE PANEL CASTING (26.04.11)

    
    
PILE CAP CASTING (26.04.2011)

    
    
STAGING IN PROGRESSING (27.04.2011)

    
    
SIDE SHUTTERING MATERIALS (27.04.2011)

    
 
    
PILE CAP SHUTTERING (28.04.2011)

    
    
PILE CAP CONCRETING (28.04.2011)

      
 

 

 

 

 

 

 

 