   weekly progress as on 29.4.2011
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaingfor completion as per the weekly plan

Remarks

Activities which can be completed without caution

1

Re wall towards NH side

100%

34

66

22

0

0

0

0

 39 days

.

2

Approach

 Span

 

5

 

4

1

28

-

-

-

-

 

 

3

Pier cap

2no

1

3

30

 0

 0

 0

 0

 46

 

4

Pile (Rly)pulikakadavuside

4

4

 

0

49

 0

 0

16

 

5

Pile (Rly)Nhside

4

4

0

49

0

0

0

0

16

 

6

Piers (Rly)

 

2No

1

3

40

 0

 0

 0

 0

 

 

9

R0AD WORK

{WBM}

100%

80%

 

20%

 

 10

 10%

 

 

 

WBM  work completed 100%

10

GIRDER

(P2-P3)

3

1

2

29

1

1

0

1

69 days

Design clarification awaited from CVCC

11

 pile cap

2

1

 

 

 

 

 

1

0

reinforcement and shuttering  of pilecapP1 is in progress.

 

Kerband hand Rail towards Pulikkakadavuside completed 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

15

27

Remarks

 

Fine Aggreagate(m3)

 6

 9

 .

 

Cement(bag)

 12

 15

 

 

Steel(MT)

 4

14

 

 

 RE Blocks

 

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

  

 

DATE

23-4-2011

24-4-2011

25-4-2011

26-4-2011

27-4-2011

28-4-2011

Weather

Rain in the evening

Sunny

Rainy in the evening

Sunny

Sunny

sunny 

 
Back
 
    
PILE CAP REINFORCEMENT WORK 28.4.2011(3).

    
    
PILE CAP REINFORCEMENT WORK 28.4.2011

    
    
GIRDER REINFORCEMENT ON BOTH SIDES COMPLETED 28.4.2011

    
    
PILE CAP REINFORCEMENT AT P1 26.4.2011

    
 
    
PILE CHIPPING WORK IN PROGRESS 23.4.2011

    
    
GIRDER REINFORCEMENT WORK IN PROGRESS 23.4.2011

      
 

 

 

 

 

 

 

 