Prevoius Weekly Reports

   progress as on 29.4.2011
    

 

Progress Report For Ponnurunni  ROB for the week ending on 29-04-2011

Si No 

Activity Description 

Total Quantity

Cumulative progress upto last week 

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week 

Actual work done during the week 

Cumulative delay in Qty up to this week

Work  Planned for next week 

No of days remaing for completion as per the weekly plan

Remarks 

1

PILE towards Palarivattom side

31

16

15

 nil

4

4

0

9

25

 

2

PILE towards vytilla side

40

0

 40

 nil

  

  Shifting of Utilities          

 

KWA Joint Inspection with Axe and AE,KWA,Pallimukku 21.2.2011 DD submitted
Joint Inspection with AE,AXE and EE KWA 2.4.2011  
BSNL Joint Inspection with DE, BSNL,Palarivattom 23.3.2011 DE,informed that there is no BSNL cable to be  removed
Joint Inspection with AE,BSNL 11.4.2011 Estimate is to be received
BPCL Joint Inspection with BPCL 24.3.2011 Span RP1-P9 changed
KSEB  Joint Inspection with Sub Engineer, KSEB 23.3.2011 DD submitted to Ae KSEB
Joint Inspection with AE,KSEB 11.4.2011 for shifting Electrical posts near the level cross 
 
Back
 
    
TREES NEAR P11 IN RAILWAY LAND IS CUT AND STACKED 21.4.2011

    
    
CONCRETING OF P16 OF P2 27.4.2011

    
    
CONCRETING OF P16 OF P2 27.4.2011

    
    
BORING AT P16 OF P2 26.4.2011

    
 
    
BORING AT P11OF P4 28.4.2011

    
    
BORING AT P11OF P4 28.4.2011

    
    
BAR BENDING WORKS FOR PILING 25.4.2011

    
 
 
 

 

 

 

 

 

 

 