   29.04.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 29-04-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed   pedestal concreting 2 No.s completed P7 & P8
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 0.00% 76.00% 10.00% 95 days  
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 0.00% 43.00% 5.00% 95 days  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 65 days  
12 BEAM/SLAB M.C SIDE 12 3 9 0 1 0 4 1 132 days concreting of 3 spans in the M.C side completed..reinforcement work and shuttering work of the girder of the fourth  span P13-P12 is completed. Side shuttering and reinforcement of deck slab in progress.deshuttering work of the span P9-P10 completed except the beam bottom.concreting of the span P13-P12  to be done on april 30th.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 53 days  
14 HR/FP/KERB M.C SIDE 100% 3 95% 0 2.00% 2.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

 

Availbility of Men           
Date 23-4-'11 24-4-2011 25-4-2011 26-4-2011 27-4-2011 28-4-2011
Nof labours 18 18 18 18 19 19 

 

 

 

Material Stocking Status      
  Required Available Remarks
Fine aggregate {cft} 100 450  
Cement(bag) 630 770  
Steel inT 11 18 sufficient material available at the site
Coarse Aggreagate (cft) 400 800   

 

 

Utility shifting    
Utilities to be shifted   Remarks
BSNL  CABLE REROUTED The BSNL has laid new cables to rerouted at the site but  to be connect the joints to the the joints. Hence no hindrance for canal deviation work.
KSEB already shifted  
KWA  hindrance The KWA has rerouted the new PVC pipelines and connected them .Therefore no hindrance.
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.  
  canal diversion work will be started soon after closing the  water flow.   
 
Back
 
    
DESHUTTERING OF THE SPAN P9, P10 23.04.2011

    
    
SHIFTING OF WATER SUPPLY PIPE LINE 23.04.2011

    
    
SHUTTERING AND REINFORCEMENT WORK OF SPAN P 13, P12 - 25.04.2011

    
    
REINFORCEMENT WORK FOR SPAN P 13 - P12 27.04.2011

    
 
    
REINFORCEMENT WROK FINISHING STAGE OF SPAN P 13 - P12 28.04.2011

      
 

 

 

 

 

 

 

 