SlNo |
Utilities |
Activities |
Date |
Status |
Remarks |
1 |
KWA |
Joint Inspection with AE,KWA,Angamali |
17.3.2011 |
DD submitted |
Pipe lines to be shifted |
2 |
BSNL |
Joint Inspection with DE, BSNL,Angamali |
17.3.2011 |
Estimate to be received |
|
3 |
KSEB |
Joint Inspection with Sub Engineer, KSEB,Karukutti |
23.3.2011 |
DD submitted |
Electric lines to be shifted |
4 |
|
Joint Inspection with AE,KSEB,Angamali |
8.4.2011 |
Estimate to be received |
|
5 |
KWA |
Joint Inspection with AE,Project division,KWA,Aluva |
1.4.2011 |
DD submitted |
Pipe lines to be shifted |
work status
-
Drain 18m(without covering slab) out of completed.
-
Cutting, bending and placing of reinforcement for Base slab and side wall of drain in progress.
-
Excavation was delayed due to hard laterite soil strata.
|