SlNo
|
Activities
|
Date
|
Remarks
|
1
|
Joint Inspection with AE,KWA,Angamali
|
17.3.2011
|
Estimate received and action taken for remitting the amount
|
2
|
Joint Inspection with DE, BSNL,Angamali
|
17.3.2011
|
Estimate is to be received
|
3
|
Joint Inspection with Sub Engineer, KSEB,Karukutti
|
23.3.2011
|
Estimate received and action taken for remitting the amount
|
4
|
Joint Inspection with AE,Project division,KWA,Aluva
|
1.4.2011
|
Estimate received and action taken for remitting the amount
|
5
|
Joint Inspection with AE,KSEB,Angamali
|
8.4.2011
|
Estimate is to be received
|
-
Cutting, bending and placing of reinforcement for Base slab and side wall of drain completed.
-
Concreting of base slab for drainage 53 meterout of 173m completed.
-
Shuttering work for side wall of drainage 53 Meter in progress
Excavation in progress, but delayed due to hard laterite soil strata
|