Prevoius Weekly Reports

   weekly progress 22.4.2011
    

 

 

Progress Report For Ponnurunni  ROB for the week ending on 22-04-2011

Si No 

Activity Description 

Total Quantity

Cumulative progress upto last week 

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week 

Actual work done during the week 

Cumulative delay in Qty up to this week

Work  Planned for next week 

No of days remaing for completion as per the weekly plan

Remarks 

1

PILE towards Palarivattom side

31

10

21

 

4

4

0

9

25

 

2

PILE towards vytilla side

40

0

 

 

 

 

 

 

 

 

 

  Status of utility relocation    
SlNo Activities Date  Remarks
1 Joint Inspection with Axe and AE,KWA,Pallimukku 21.2.2011 Estimate is to be received
2 Joint Inspection with DE, BSNL,Palarivattom 23.3.2011 DE,informed that there is no BSNL cable to be  removed
 3  DE, BSNL,Vytilla   Estimate is to be received 
4 Joint Inspection with Sub Engineer, KSEB 23.3.2011 DD submitted to Ae KSEB
5 Joint Inspection with BPCL 24.3.2011  span RP1-P9 changed
Joint Inspection with AE,AXE and EE KWA 2.4.2011  Estimated is to be received
7 Joint Inspection with AE,KSEB 11.4.2011 KSEB posts at P11 shifted to LHS
8 Joint Inspection with AE,BSNL 11.4.2011  
 