   weekly progress as on 22.4.2011
    

 

Activities which can be completed without caution 

 

  Activity -Description  Total Quantity  Cumulative progress up to this week  Balance  work  Cumulative delay in weeks after  Work  planned  during the week  Actual work done during the last week  Short fall in the last week   Work   No of days remaing for completion as per the weekly plan Remarks 
-1 -2 Spplagmnt  -4 -5 -6 Planned for next week 
    -3       -7
  Re wall towards NH side  100% 34 66 21 0 0 0 0  46 days  .
  Approach  5 4 1 28     
 Span
  Pier cap  2no  1 3 29  0   0   0   0   53   
  Pile (Rly)pulikakadavu side  4 4 0 48  0  0   0    0  23  
  
  Pile (Rly)Nh side 4 4 0 48 0 0 0 0 23  
  Piers (Rly) 2No  1 3 39  0   0   0   0     
  R0AD WORK 100% 90%WBM completed. 0     15   30%       46 days  WBM  3rd layer completed. In the pulikkakadavu side.
  Girder 15 13 2 29 1 1 0 1 69 days Concreting of the girder  in the span P2-P3 iplanned for the next week
 
  Pile cap at P1                 0 Pile chipping is in progress
Kerb and hand rail towards Pulikkakadavu side completed 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab 

 
Back
 
    
REINFORCEMENT FOR GIRDER 2 20.4.2011

    
    
PCC COMPLETED FOR PILE CAP AT P1 IN THE NH SIDE

    
    
GIRDER 1 REINFORCEMENT WORK IN PROGRESS 18.4.2011

    
    
GIRDER 1 REINFORCEMENT WORK IN PROGRESS 16.4.2011

    
 
    
GIRDER 1 REINFORCEMENT WORK IN PROGRESS 16.4.2011

    
    
GIRDER 1 CONCRERTING COMPLETED 19.4.2011

    
    
CABLE PROFILE WORK IN PROGRESS 16.4.2011

    
 
    
STAGGING ARRANGEMENTS FOR GIRDER 2 -19.4.2011

      
 

 

 

 

 

 

 

 