Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886648
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly report as on 22.04.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 22-04-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed    
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 0.00% 66.00% 10.00% 102 days  
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 0.00% 33.00% 5.00% 102 days  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 72 days  
12 BEAM/SLAB M.C SIDE 12 3 9 0 1 1 1 1 132 days concreting of 3 spans in the M.C side completed.concreting of the span P9-P10 over.reinforcement work and shuttering work of the girder of the fourth  span P13-P12 in progress. staging work of the span P8-P7 in progress.deshuttering work of the span P9-P10 in progress 
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 53 days  
14 HR/FP/KERB M.C SIDE 100% 3 95% 0 2.00% 2.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

 

Availbility of Men            
Date 16-4-'11 17-4-2011 18-4-2011 19-4-2011 20-4-2011 21-4-2011
Nof labours 20 20 20 20 20 25 

 

 

Material Stocking Status          
  Required Available Remarks      
Fine aggregate {cft} 100 500        
Cement(bag) 630 770        
Steel inT 11 18 sufficient material available at the site      
Coarse Aggreagate (cft) 400 600        

 

 

Utility shifting    
Utilities to be shifted   Remarks
BSNL  hindrance talked to the BSNL in charge of the locality.agreement made to re-route the cable.
KSEB already shifted  
KWA  hindrance given the letter to the AE and AXE of the water authority, thrissur, to visit the site and take the estimate of the rerouting cost as soon as possible. The hindrance is in the west side of canal.
Others WBM completed, BM to be started  
  canal diversion work will be started after 30th of this month.  
  THE WATER AUTHORITY HAS STARTED THE TRANCHING WORK FOR THE PIPE LINE SHIFTING.THE BSNL AUTHORITIES INFORMED  THEY WILL RE-ROUTE THE CABLES AFTER THE TRENCHING  WORK FOR THE KWA PIPELINE.  
  THE  CANAL WORK CANNOT BE STARTED AS THE CANAL IS FILLED WITH WATER.   
 
Back
 
    
DESHUTTERING OF SPAN P9-P10 - 16.04.2011

    
    
REINFORCEMENT WORK FOR SLAB P13-P12 - 18.04.2011

    
    
REINFORCEMENT WORK FOR PEDESTAL - 19.04.2011

    
    
STAGING WORK FOR 5TH SPAN - 19.04.2011

    
 
    
EARTH WORK EXCAVATION FOR SHIFTING WATER SUPPLY PIPELINE - 20.04.2011

    
    
SHUTTERING AND BARBENDING WORK OF SPAN P13-P12 -20.04.2011

    
    
SHUTTERING AND BARBENDING WORK OF P13-P12 - 21.04.2011

    
 
 
 

 

 

 

 

 

 

 