Work Planned upto 31/7/2010 |
Completed / Progress |
Remarks |
P3-P4 Span |
|
|
Concreting of Slab & Stressing |
Completed |
|
Approval of GAD by railways (Railway Portion) |
Approved |
Approved on 1-5-10 |
Preparation of Design and Drawing |
In progress |
Superstructure drawings not submitted by the contractor |
Under Pass Wall concreting 3rd lift & slab |
Completed |
|
Casting of foot path slab |
|
|
Bar bending for retaining wall/ Handrail |
in progress |
|