Prevoius Weekly Reports

   18.08.2010
    

 

ROB at Bakel

PROGRESS OF ROB WORK AS ON 14.08.2010
 
Work Planned upto 14-08-2010 Completed/ Progress Remarks
Span on Kasargod side    
Hand rail casting In progress  
Span on Kannur Side    
Shuttering work for 3 nos beams Progress Road Blocked on 24.07.2010
New projects    
 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 