   Weekly report as on 15.04.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 15-04-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9 Completed    
2 PILE M.C SIDE 36 36 Completed    
3 PILE CAP SHORNUR SIDE 3 3 Completed    
4 PILE CAP  M.C SIDE 12 12 Completed    
5 PIER SHORNUR  SIDE 3 3 Completed    
6 PIER M.C SIDE 12 12 Completed    
7 PIER CAP SHORNUR  SIDE 3 3 Completed    
8 PIER CAP M.C SIDE 12 12 Completed    
9 RE/R WALL SHORNUR  SIDE 100% 9 91% 0 10.00% 0.00% 56.00% 10.00% 109 days PCC laid for 65 square metre shortage  of labour seriously affecting the progress of the work.in the shornur side approach.
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 0.00% 28.00% 5.00% 109 days  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 79 days  
12 BEAM/SLAB M.C SIDE 12 2 10 0 1 1 1 1 139 days concreting of 3 spans in the M.C side completed.concreting of the span P9-P10 over.reinforcement work of the girder of the fourth  span P13-P12 in progress. 
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 53 days  
14 HR/FP/KERB M.C SIDE 100% 3 97% 0 2.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

Availbility of Men 

             
Date 09-4-'11 10/4/2011 11/4/2011 12/4/2011 13-4-2011 14-4-2011 15-4-2011
Nof labours 25 25 24 44 27 27 27 

 

 

 

Material Stocking Status    
  Required Available Remarks
Fine aggregate {cft} 300 700  
Cement(bag) 630 770  
Steel inT 10 13 sufficient material available at the site
Coarse Aggreagate (cft) 600 800   

 

 

Utility shifting    
Utilities to be shifted   Remarks
BSNL  hindrance talked to the BSNL in charge of the locality.agreement made to re-route the cable.
KSEB already shifted  
KWA  hindrance Pipe line shifting charge remitted to EE,KWA, PH Division, Thrissur
Others road diversion work    IN PROGRESS.only bitumenous macadum layer is left to be done.  
  The canal deviation work to be commenced soon after clearing of KWA line and BSNL cable. 
 
Back
 
    
REINFORCEMENT WORK FOR P9-P10 - 09.04.2011

    
    
REINFORCEMENT WORK FOR P9-P10 - 10.04.2011

    
    
ARRANGEMENTS FOR CONCRETING OF SPAN P9-P10 - 11.04.2011

    
    
CONCRETING OF BEAM OF SPAN P9-P10 - 12.04.2011

    
 
    
CONCRETING OF DECK SLAB - 12.04.2011

      
 

 

 

 

 

 

 

 